Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 19104MF12P01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a Utility Construction Services Agreement with CenterPoint Energy Houston Electric, LLC, in the amount of $210,216.53 for overhead electric lines and power poles relocations, in connection with Memorial Hills Subdivision Drainage Improvements - 2018, UPIN 19104MF12P01, Precinct 1.
end
Background and Discussion:
The project is located in north Harris County in the Cypress Creek watershed, north of FM 1960, south of Cypress Creek, and east of Hardy Toll Road. The project area consists of approximately 84 acres of single-family residential homes. The existing system is a concrete curb and gutter and primarily drains into Briar Creek (K117-00-00). The scope of the project includes constructing a drainage swale and underlying storm sewer behind the commercial tract along FM 1960.
Expected Impact:
This project seeks to reduce flooding by assisting in the alleviation of structural flood damage to the community. This agreement is a step to reduce the financial, and physical burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the surrounding neighborhoods and Harris County. The execution of this agreement will allow CenterPoint Energy Houston Electric, LLC to relocate their low overhead electric lines and power poles.
Alternative Options:
The County could elect to fund the requested task or choose to reject it. However, if not approved, the project will not be constructed as designed.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any): N/A
Date |
Agenda Item # |
Action Taken |
|
|
|
Location: Memorial Hills Subdivision
Address (if applicable): N/A
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
Engineering |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
1080 - Infrastructure Fund |
$ |
$210,216.53 |
$210,216.53 |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$210,216.53 |
$210,216.53 |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$210,216.53 |
$210,216.53 |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: September 19, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): Utility Construction Services Agreement