File #: 25-3443    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 5/27/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval to execute an agreement with Midtown Engineers, LLC in the amount of $840,313.00 for Professional Engineering and related services in connection with Subdivision Improvements - Highlands - 2024, UPIN 24208MF3F901, Precinct 3, MWBE Contracted Goal: 3.77%.
Attachments: 1. 25-3443-Award-24208MF3F901-Midtown Engineers,LLC-Subdivision Improvements -Highlands-2024-P3

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 24208MF3F901

Vendor/Entity Legal Name (if applicable): Midtown Engineers, LLC

 

MWBE Contracted Goal (if applicable): 3.77%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Midtown Engineers, LLC in the amount of $840,313.00 for Professional Engineering and related services in connection with Subdivision Improvements - Highlands - 2024, UPIN 24208MF3F901, Precinct 3, MWBE Contracted Goal: 3.77%.

end

 

Background and Discussion:

Precinct 3 is requesting the Office of the County Engineer to enter into an agreement for professional engineering services to remove the roadside ditches, and construct five-foot-wide sidewalks by installing a storm sewer system for subdivisions in the Highlands area.  The study phase will cover the entire area, with Phase One focusing on design and construction.  The Highlands area is bounded by West Canal Road to the north, Crosby Lynchburg Road to the east, Harris Road to the south and the San Jacinto River to the west.

 

Expected Impact:

The project will ensure the subdivisions in the Highlands community are maintainable and functional.

 

Alternative Options:

Without this project, the roads cannot be maintained properly. The goal is to enhance safety, pedestrian flow, and drainage, as requested by Precinct3.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06/04/2024

146 (24-3251)

Request for approval to negotiate with Midtown Engineers, LLC for professional engineering services in connection with Subdivision Improvements - Highlands - 2024, UPIN 24208MF3F901, Precinct 3.

 

Location:

Address (if applicable): Various subdivisions in the Highlands area - Highlands, TX 77562

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1040 - FLEX Fund

$

$840,313.00

$840,313.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$840,313.00

$840,313.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$840,313.00

$840,313.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/12/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services,