Legislation Details

File #: 24-5084    Version: 1 Name:
Type: Report Status: Passed
File created: 8/13/2024 In control: Commissioners Court
On agenda: 8/27/2024 Final action: 8/27/2024
Title: Request for approval of a Study Report prepared by KIT PROFESSIONALS, INC., for Prado Woods Subdivision Drainage Improvements - 2018, UPIN 19103MF16N01, Precinct 3.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Report

 

Project ID (if applicable): UPIN 19103MF16N01

Vendor/Entity Legal Name (if applicable): KIT PROFESSIONALS, INC.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a Study Report prepared by KIT PROFESSIONALS, INC., for Prado Woods Subdivision Drainage Improvements - 2018, UPIN 19103MF16N01, Precinct 3.

end

 

Background and Discussion:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This study report is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the Prado Woods subdivision. The scope and proposed improvements consist of upsizing storm sewer system and repaving the road.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood in the Prado Woods subdivision. No impact to project cost, schedule or staffing anticipated.

 

Alternative Options:

The County could elect to approve or choose to reject the study recommendations. However, if not approved, the design plans cannot be completed as recommended in the study.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

03/30/2021

21-1141

Authorization to Negotiate for Engineering Services

06/29/2021

21-3121

Professional Services Agreement

10/26/2021

21-5655

Professional Services Agreement Amendment

04/26/2022

22-2485

Professional Services Agreement Amendment

 

Location: Prado Woods St

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: August 27, 2024

Anticipated Implementation Date (if different from Court date): August 28, 2024

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): Study Report