Title: Request for approval of a change in contract with Conrad Construction Co., Ltd. in connection with Anderson Road - Hiram Clarke Road to Almeda Road - 2018, adding 18 calendar days, with an addition in the amount of $147,253.50, Job No. 23/0152-5, UPIN 19101MF0XY01, Precinct 1, MWBE Contracted Goal: 21%.

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0152, UPIN 19101MF0XY01

Vendor/Entity Legal Name (if applicable): Conrad Construction Co., Ltd.

 

MWBE Contracted Goal (if applicable): 21%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Conrad Construction Co., Ltd. in connection with Anderson Road - Hiram Clarke Road to Almeda Road - 2018, adding 18 calendar days, with an addition in the amount of $147,253.50, Job No. 23/0152-5, UPIN 19101MF0XY01, Precinct 1, MWBE Contracted Goal: 21%.

end

 

Background and Discussion:

Project includes completion of the two-lane concrete curb and gutter road with sidewalk on both sides and left turn lanes at the intersections approximately 7,800 linear feet of Anderson Road construction from 500 feet west of Hiram Clark Road to Almeda Road/FM 521 (Segment 2).

 

This change in contracts includes:

PCO-20- Quantity overruns of exist. Items = $141,738.50 and additional of 15 Days.

PCO-21-Item 41- 24” RCP=$1,240.00 and Item 27- driveway #43 for HES concrete = $4,275.00 and additional of    3 Days.

 

Expected Impact:

Changes allow for compensation to the Contractor for actual quantities used in construction, in accordance with the original intent of the project.

 

 

Alternative Options:

Revise original scope of the project.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  G1: Expand pedestrian and cyclist infrastructure on County-managed roads,

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06/27/2023

254 (23-3490)

Contract Award

06/25/2024

49 (24-3586)

Contract Amendment #1 for additional funds and extension of project term

08/06/2024

52 (24-4706)

Contract Amendment #2 for additional funds and extension of project term

10/08/2024

50 (24-6046)

Contract Amendment #3 for additional funds and extension of project term

03/27/2025

104 (25-2025)

Contract Amendment #4 for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund   3109

$

$147,253.50

$147,253.50

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$147,253.50

$147,253.50

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$147,253.50

$147,253.50

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/8/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B