Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): 20104MF1BM01
Vendor/Entity Legal Name (if applicable): Arcadis, U.S., Inc.
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by Arcadis, U.S., Inc. for Grant Road Segment 4 - from Cypress Rose Hill Road to Telge Road - 2018, UPIN 20104MF1BM01, Precinct 3.
end
Background and Discussion:
This project is located at Grant Road in Precinct 3 and is adjacent to other capital improvement projects.
Expected Impact:
This Study Report will provide the necessary information to proceed with the proposed road improvement project which consists of a 4-lane concrete boulevard in a 100-foot ROW with a 32-foot raised median, underground storm sewer, detention mitigation, and sidewalks.
Alternative Options:
The County could elect to approve or choose to reject the study recommendations. However, if not approved, the design plans cannot be completed as recommended in the study.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Strengthen the County’s commitment to Vision Zero principles and goals.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan:
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
4/9/2019 |
1.f.1 |
Authorization to Negotiate |
|
5/19/2020 |
1.g.13 |
Agreement |
|
8/6/2024 |
51 |
Amendment #1 |
Location: Grant Road
Address (if applicable): Grant Road
Precinct(s): Precinct 3
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Other |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$ |
$ |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 10/30/2025
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item
Contact(s) name, title, department: Truitt Rounsavall, P.E., PMP, MBA, LSSBB, ECPBM, Capital Project Horizontal Director, Office of the County Engineer.
Attachments (if applicable): Study Report