Title: Request for approval to execute an agreement with IDS Engineering Group, Inc., in the amount of $125,622.24 for Construction Phase Services in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, UPIN 22102MF2G801, Precinct 2, MWDBE Contracted Goal: 20%.
Sponsors: Mony Hossain
Attachments: 1. 24-5259-Award-UPIN 22102MF2G801-CPS-Vickery Intersection-IDS-P2-08-27-2024

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 22102MF2G801

Vendor/Entity Legal Name (if applicable): IDS Engineering Group, Inc.

 

MWDBE Contracted Goal (if applicable): 20%

MWDBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):                      

title

Request for approval to execute an agreement with IDS Engineering Group, Inc., in the amount of $125,622.24 for Construction Phase Services in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, UPIN 22102MF2G801, Precinct 2, MWDBE Contracted Goal: 20%.

end

 

Background and Discussion:

The project is in North Harris County in the Green’s Bayou and Hall’s Bayou watershed, south of Beltway 8, east of Highway 69.  The project consists of Intersection improvements including sidewalks, roadway widening, and the installation of a new traffic signal. The project limits include the intersection of Vickery Street and Lauder Road with approximately 870 feet of roadway improvement at Lauder Rd, 300 feet at Vickery Street and 800 feet at WE Crowley Park Road.

 

Expected Impact:

This project seeks to enhance vehicular mobility by improving roadway conditions along Vickery Street, Lauder Road, and WE Crowley Park Road. The Goal of the project is to improve overall pedestrian and vehicular mobility in the area.

 

Alternative Options:

If no action is taken, the project may experience delays in improving mobility in the area.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/14/2021

21-6764

Request for approval to negotiate with IDS Engineering Group, Inc. for Professional Engineering Services in connection with Intersection Improvement at Vickery Street and Lauder Road - 2021, UPIN 22102MF2G801, Precinct 2.

05/10/2022

22-2937

Request for approval to execute an agreement with IDS Engineering Group, Inc. in the amount of $455,412.30 for Professional Engineering Services to provide intersection improvements to Vickery Street at Lauder Road, UPIN 22102MF2G801, Precinct 2.

09/13/2022

22-5535

Request for approval of a Study Report prepared by IDS Engineering Group for Intersection Improvement - Vickery Street at Lauder Road - 2021, UPIN 22102MF2G801, Precinct 2, MWDBE Current Participation 20%.

 

Location: Intersection or Vickery Street and Lauder Road

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3021

$

$73,474.17

$73,474.17

$

Other 3109

$

$52,148.07

$52,148.07

$

Choose an item.

$

$

$

$

Total Current Budget

$

$125,622.24

$125,622.24

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$125,622.24

$125,622.24

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: August 27, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Agreement