Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E. PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN# 20035MF1GW01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC
MWDBE Contracted Goal (if applicable): NA
MWDBE Current Participation (if applicable): NA
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a Facilities Extension Agreement with CenterPoint Energy Houston Electric, LLC, and authorize the County Auditor to approve a Purchase Order in the amount of $18,095.00 for the cost associated for multiple points of service in connection with Riverside at 2931 Holman Street, Houston, TX 77004, which to include all deposit/fees for utility services, UPIN 20035MF1GW01, Precinct 1.
end
Background and Discussion: CenterPoint requires a signed Facilities Extension Agreement for the construction of the multiple points of service. CenterPoint charges a fee for a nonstandard service.
Expected Impact: The agreement and payment are required for the project to move forward.
Alternative Options: There are no alternate options as CenterPoint is the one and only entity we can deal with in these matters for electric service.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
X Public Health
_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
2/21/2023 |
174 |
Approval of Final Investment Memo for Riverside Revitalization Project for an additional authorization additional authorization of $27,961,391.00 for a total authorization of $38,298,041.00. |
Location:
Address (if applicable): 2931 Holman Street Houston, Tx 77004
Precinct(s): Precinct 1
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Commercial Paper |
$ |
$18,095.00 |
$18,095.00 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$18,095.00 |
$18,095.00 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$18,095.00 |
$18,095.00 |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: May 7,2024
Anticipated Implementation Date (if different from Court date): NA
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Ross Hosket, P.E., CFM, Env SP, Interim Director of
Capital Project Facility Division, Harris County Engineering Department
Attachments (if applicable): Facility Extension Agreement