Legislation Details

File #: 24-5216    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/15/2024 In control: Commissioners Court
On agenda: 8/27/2024 Final action: 8/27/2024
Title: Request for approval of a change in contract with Bear Services, LP, in connection with final construction of Sidewalk - Bentley Road from Kowis Street to Hopper Road - 2021, with a deduction in the amount of $4,505.98, Job No. 21/0365-2, UPIN 22102MF2FB01, Precinct 2, MWDBE Contracted Goal: 16%, MWDBE Current Participation: 23.01%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0365, UPIN 22102MF2FB01

Vendor/Entity Legal Name (if applicable): Bear Services, LP

 

MWDBE Contracted Goal (if applicable): 16%

MWDBE Current Participation (if applicable): 23.01%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Bear Services, LP, in connection with final construction of Sidewalk - Bentley Road from Kowis Street to Hopper Road - 2021, with a deduction in the amount of $4,505.98, Job No. 21/0365-2, UPIN 22102MF2FB01, Precinct 2, MWDBE Contracted Goal: 16%, MWDBE Current Participation: 23.01%.

end

 

Background and Discussion:

Project includes the construction of new sidewalks and driveways along both sides of Bentley Street from Kowis Street to Hopper Road.  This change in contract includes the final reconciliation of actual quantities used in construction against the bid quantities. Total = - ($4,505.98)

 

Expected Impact:

This action allows for unused funds to be returned to Harris County.

 

Alternative Options:

Action required to return unused funds.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/14/2021

21-6856

Contract Award

10/10/2023

23-6009

Contract Amendment for extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

-$4,505.98

-$4,505.98

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

-$4,505.98

-$4,505.98

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

-$4,505.98

-$4,505.98

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date:  August 27, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B