Title: Request for approval of a Change Investment Memo for the Downtown Complex Tunnel System Repair and Mitigation projects, for an incremental amount of $1,500,000.00 for a total of $5,467,400 and a request for approval of commercial paper funding in the amount of $1,500,000.00 for a total allocation of $5,470,000.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP

Managing Department: County Engineer

Managing Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Change Investment Memo

 

Project Name: Downtown Complex Tunnel System Repair and Mitigation

Project ID (if applicable): MF0X2

                                              Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $1,500,000

Total Estimated Project Cost: $5,467,400

 

Request Summary:

title

Request for approval of a Change Investment Memo for the Downtown Complex Tunnel System Repair and Mitigation projects, for an incremental amount of $1,500,000.00 for a total of $5,467,400 and a request for approval of commercial paper funding in the amount of $1,500,000.00 for a total allocation of $5,470,000.

end

 

 

Project Description:

The purpose is to upgrade the Caroline Street Tunnel (FEMA to reimburse the funds).  FEMA covers two projects in their scope:

1.                     Construction of the Downtown Tunnel Flood Mitigation Lift Station (currently under construction)

2.                     Construction of the Restoration of the Caroline Street Tunnel

This request is for the construction of the restoration of the Caroline Street Tunnel, which involves demolition and refurbishment of damaged floor, walls, and ceiling surfaces and finishes, as well as electrical light fixtures. These refurbishments will include mitigation upgrades, such as resilient wall panels and polished concrete flooring surfaces, to minimize damage during future flooding events. Due to rising costs since 2018, the project requires an increase in authorization of $1,500,000 to reach the final milestone.

 

Project Scope:

The Construction of the Restoration of the Downtown Tunnels has a FIM previously approved by the Commissioners Court. Since 2017, several actions have been taken for this project, which include: assessments performed on the Caroline Street Tunnel, provision of recommendations for repairs and replacements of certain components, and provision of signed and sealed construction documents.

 

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

Award for construction phase of the Caroline Tunnel Restoration Project associated with the escalation cost from 2018.

$1,000,000.00

FY 2026

Additional Professional Services - architecture and engineering services caused by an extended schedule.

$200,000.00

FY 2026

Contingency (25%)

$300,000.00

FY 2026

Total

$1,500,000.00

 

 

Justification & Alternatives:

Justification:

Hurricane Harvey affected certain operations of select County-owned buildings that are connected to the Caroline Street Tunnel system. The (pre-Harvey) equipment failed to rapidly remove stormwater from the existing tunnel system. Consequently, huge amounts of stormwater damaged floors, walls, ceiling surfaces, finishes, and electrical fixtures. To repair the damaged features of the Tunnel, restore it to pre-Harvey conditions, as mentioned, and prevent/or hinder similar occurrences in future flooding events, there is a need to approve funding for the construction phase of this project.

Alternatives and Engagement:

If the requested (CIM) Change Investment Memo isn’t approved by the Commissioner’s Court, the construction phase of this project will be unable to commence, thus preventing the Caroline Street Tunnel from being restored to its pre-flooding condition. Given that the Construction of the Downtown Tunnel Flood Mitigation Lift Station project only exists because of the Construction of the Restoration of the Caroline Street Tunnel project, the reimbursements from FEMA will be jeopardized if the Flood Mitigation project is executed without the Restoration of the Caroline Street Tunnel project.

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  I1: Develop a countywide parks network and connectivity plan.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Previous Court Action:

Date

Agenda Item #

Action Taken

4/10/18

19.d.8.c

Johnston, LLC, in the amount of $394,500 for architectural and engineering services for the design of restoration and mitigation efforts on county buildings for the period of April 10, 2018-April 9, 2019 (17/0274).

8/13/2019

18.d.14.b

Request that the County Judge execute amendments with:  • Lockwood, Andrews & Newnam, Inc.; Collaborate Arch, LLC; Johnston, LLC; Rey de la Reza Architects, Inc., dba RdlR Architects, Inc.; Page Southerland Page, Inc.; and PGAL, Inc., to incorporate provisions now required by law for architectural and engineering services for the design of restoration and mitigation efforts on county buildings, with no increase in the total contract amount (17/0274).

10/29/19

II.4

Request by the Purchasing Agent that the County Judge executes the third amendment to the agreement with Page Southerland Page, Inc. in the additional amount of $305,000 for professional architectural and engineering services for the design of restoration and mitigation efforts on Harris County buildings (170274).

1/7/20

1.p.3

Recommendation for approval of funding of the FY 2020 Capital Improvements Program projects for:  • Downtown complex tunnel system repairs in the amount of $350,000.

1/28/2020

4.g.5

Request for approval of commercial paper funding for the Office of the County Engineer for the:  • Downtown complex tunnel system repairs project in the amount of $350,000.

  8/11/20

19.c.9.b

 Request that the County Judge execute amendments to agreements with:  • Page Southerland Page, Inc., in the additional amount of $48,000 for additional work for architectural and engineering services for the design of restoration and mitigation efforts on county buildings (170274).

2/9/21

224

Request that the County Judge execute an amendment to an agreement with Johnston, LLC, in the additional amount of $149,500 for flood mitigation efforts to be implemented in the Harris County downtown tunnel system for architectural and engineering services for the design of restoration and mitigation efforts on county buildings (170274).

8/10/21

110

Request for Authorization for the Facilities and Property Maintenance (FPM) Division to Bid for Construction On, and Receive Funding for the Restoration and Mitigation of the Downtown Tunnel System - Caroline St. Tunnels (Harvey) Project, in the Amount of $460,000.00, Precinct 1

11/30/21

21-6212

Request for approval of a Preliminary Investment Memo for the Downtown Complex System Repairs project, Caroline St. Tunnels Mitigation phase, for an additional $259,900 for a total authorization of $1,413,300 and commercial paper funding for an additional $260,000 for a total of $610,000, Precinct 1.

5/10/22

22-2973

Request for approval of a Change Investment Memo for the Downtown Complex Tunnel System Repair and Mitigation projects in the additional amount of $97,500 for a total authorization of $1,714,400 and commercial paper funding for an additional $100,000 for a total allocation of $710,000, UPIN 18035MFOX201, Precinct 1.

6/14/2022

22-3562

Request that the County Judge execute amendments to agreements with:  • Page Southerland Page, Inc., in the additional amount of $48,000 for additional work for architectural and engineering services for the design of restoration and mitigation efforts on county buildings (170274).

8/23/2022

Agenda #:325

Request that the County Judge execute an amendment to an agreement with Johnston LLC, additional amount of $281,000 for flood mitigation efforts to be implemented in the Downtown Tunnel System for professional architectural and engineering services for the design of restoration and mitigation efforts on Harris County buildings (170274).

8/8/2023

23-4530

Request for approval of a Final Investment Memo for the Downtown Tunnel System (Harvey) project in the amount of $2,800,000 for a total authorization of $4,511,400.

5/08/2025

25-2906

Transmittal by the office of the Purchasing Agent of a project scheduled for advertisement for construction of the downtown tunnel flood mitigation lift station for Precinct 1.

8/26/2025

25-5493

Request by the Office of Management and Budget for approval of commercial paper funding for the Office of the County Engineer for the Downtown Complex System Repairs and Mitigation project in the additional amount of $2,810,000 for a total CP funding of $3,970,000.

9/18/2025

25-5962

Request for approval of an award based on low bid to MC2 Civil, LLC in the amount of $3,194,500 for construction of the Downtown Tunnel Flood Mitigation Lift Station for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (250131), MWBE Contracted Goal: 9.12%.

                     

Address: 201 Caroline Street

Precinct(s): Countywide

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$1,500,000

$1,500,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$1,500,000

$1,500,000

$

Total Funding Request

$

$1,500,000

$1,500,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/29/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, Special Assistant County Attorney, 1/21/2026

Department Approval by: Erwin Burden, P.E, CFM, Chief of Engineering and Architectural Services

Office of the County Engineer

OMB CIP Team Approval by: Wanwei Tang, Analyst - Capital Projects and Infrastructure, 1/20/2026

Commercial Paper Request (For OMB use only):

Receiving Department: County Engineer

Project PeopleSoft ID: MF0X2

CP Series Description: Commercial Paper Series D-2 can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the Downtown Complex Tunnel System Repair and Mitigation project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.

Note: Commercial Paper is issued in increments of $5,000 and the excess is not available to be spent by the department.

OMB Financial Management contact: Fahad Gulzar, Acting Deputy Executive Director, Office of Management and Budget