Legislation Details

File #: 24-3630    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/11/2024 In control: Commissioners Court
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Request for approval of a change in contract with WadeCon, LLC, in connection with Beaumont Place Subdivision Drainage Improvements, with an addition in the amount of $269,671.40, Job No. 22/0199-7, UPIN 19101MF17901, Precinct 2, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 11.48%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0199 - UPIN 19101MF17901

Vendor/Entity Legal Name (if applicable): WadeCon, LLC

 

MWDBE Contracted Goal (if applicable): 21%

MWDBE Current Participation (if applicable): 11.48%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with WadeCon, LLC, in connection with Beaumont Place Subdivision Drainage Improvements, with an addition in the amount of $269,671.40, Job No. 22/0199-7, UPIN 19101MF17901, Precinct 2, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 11.48%.

end

 

Background and Discussion:

This project is located in the Greens Bayou watershed near Highway 90 and Beltway 8. The Beaumont Place subdivision consists of mainly roadside ditches and has been subjected to several flooding events with the most recent being Hurricane Harvey (August 2017) and the Tax Day Flood (April 2016). Drainage analysis of the subdivision began in late 2019 as a part of the 2018 Bond program for subdivision drainage improvements. The scope and proposed improvements include roadside ditch regrading, driveway culvert upgrades, expansion of channel along Big Gulch, concrete lined Sulphur Gully channel with reinforced concrete box (RCB) crossing improvements. Improvements also include multiple detention ponds along Big Gulch with an extreme event overflow swale towards the upstream portion of the channel.

 

The Change in contract request includes new items for the following:

•                     PCO - 10 Quantity Overruns - Added (3,561.82 SY) to Item No. 4 - Remove and Dispose Existing Driveways (Concrete) with an additional cost of $35,618.20, Added (4,352.12 SY) to Item No. 5 - Remove and Dispose Existing Driveways (Grass and/or Gravel) with an additional cost of $21,760.60, Added (3 EA) to Item No. 9 - Removing Old Structures (Inlets) with an additional cost of $3,000.00, Added (62 EA) to Item No. 10 - Removing Old Structures (Headwalls) with an additional cost of $62,000.00, Added (94.50 LF) to Item No. 16 - Trench Safety System (5' to 10') with an additional cost of $945.00, Added (40.00 LF) to Item No. 21 - Reinforced Concrete Pipe, C76, Class III, Rubber Gasket (36") with an additional cost of $12,000.00, Added (2,421.71 SY) to Item No. 40 - Reinforced Concrete Driveway (6") (High Early Strength) with an additional cost of $266,388.10, Added (0.39 Month) to Item No. 42 - Traffic Control - Furnish-Install & Remove with an additional cost of $1,950.00, Added (12.50 CY) to Item No. 53 - Remove and Dispose Existing Structure with an additional cost of $1,250.00, Added (41 EA) to Item No. 55 - Remove Existing Tree <=16" with an additional cost of $41,000.00, Added (80 LF) to Item No. 69 - 24" RCP with an additional cost of 17,600.00, Added (16 LF) to Item No. 71 - 36" RCP with an additional cost of $4,960.00, Added (12 LF) to Item No. 75 - 5'x4' RCB with an additional cost of $8,400.00, Added (39.04 LF) to Item No. 76 - 5'x5' RCB with an additional cost of $29,280.00, Added (23 LF) to Item No. 87 - Well-Pointing (Min Bid Price $25.00/LF) with an additional cost of $575.00, and Added (292.97 SY) to Item No. 93 - Concrete Channel Lining Bottom, 8" with an additional cost of $83,244.50. A quantity deduction of (3203 SY) from Item 65 Concrete Channel Lining, 6" with a cost deduction of $320,300.00 to offset the same quantity included in the previously added item for Concrete Channel Lining Bottom, 8". The net addition of $269,671.40 reconciles actual quantities used in construction with the estimated quantities for completing the proposed scope of work.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Beaumont Place Subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the original scope of work.

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/02/2022

22-4428

Contract Award

05/16/2023

23-2888

Change Order Approved

09/19/2023

23-5373

Change Order Approved

10/31/2023

23-6463

Change Order Approved

10/31/2023

23-6214

Change Order Approved

03/26/2024

24-1617

Change Order Approved

06/04/2024

24-3109

Change Order Approved

 

Location: Beaumont Place Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 2

 

 

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

$269,671.40

$269,671.40

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$269,671.40

$269,671.40

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$269,671.40

$269,671.40

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: June 25, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Change in Contract (CIC)