File #: 25-2711    Version: 1 Name:
Type: Public Necessity Status: Passed
File created: 4/23/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action: 5/8/2025
Title: Request for approval to decree that the Harris County Flood Control District project serves a public purpose and public necessity, which requires that the Harris County Real Property Division be directed to acquire one fee simple tract for the public project known as Cedar Bayou Lynchburg Sub-Regional Stormwater Detention Basin ROW Acquisition, for the purpose of stormwater detention (Spring Gully & Goose Creek Watersheds, Bond ID Z-02, Project ID O100-00-00-R002, HCFCD Tract O100-00-00-09-008.0, Precinct 2).
Attachments: 1. 050825 PN O100-R002 PCT 2 backup.pdf

Primary Department: Flood Control District

Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Public Necessity

 

Project ID (if applicable): O100-00-00-R002

Vendor/Entity Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to decree that the Harris County Flood Control District project serves a public purpose and public necessity, which requires that the Harris County Real Property Division be directed to acquire one fee simple tract for the public project known as Cedar Bayou Lynchburg Sub-Regional Stormwater Detention Basin ROW Acquisition, for the purpose of stormwater detention (Spring Gully & Goose Creek Watersheds, Bond ID Z-02, Project ID O100-00-00-R002, HCFCD Tract O100-00-00-09-008.0, Precinct 2).        

end

 

Background and Discussion:

The propose of the project is to acquire the property for a proposed stormwater detention basin to mitigate the impacts of increased flows from road improvements in the area through the Cedar Bayou Sub-Regional Stormwater Detention Basin Right-of-Way Acquisition Project. The Flood Control District will purchase the property, while the cost of the property will be shared between the City of Baytown and the Flood Control District, with each party contributing a maximum of $1,550,000, with the total of $3,100,000 toward the acquisition of the property, under the agreement no. 2022-64.

 

Expected Impact:

It is anticipated that the purchase of this property will provide the location for a future basin, that along with other identified future projects in the watershed, will lead to the removal of 152 structures from the floodplain during 100-year storm events and 334 structures during 500-year storm events and also provide flood detention volume for the City of Baytown. 

 

Alternative Options:

Not acquiring the property would prohibit the realization of benefits for the area.

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  I4: Encourage the growth of natural habitats in County channels and improve cleanliness of green spaces while reducing debris and enhancing beautification.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/14/2021

115.

ILA

 

Location:

Address (if applicable): 3102 West Cedar Bayou Lynchburg Road, Baytown, TX 77521

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

N/A

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/8/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Findings and Declarations, Metes and Bonds, Survey and Map