Legislation Details

File #: 25-7135    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 10/29/2025 In control: Commissioners Court
On agenda: 11/13/2025 Final action: 11/13/2025
Title: Request for approval to execute an agreement with Raba-Kistner Inc. in the amount of $197,337.00 for Professional Engineering Services regarding Construction Materials Testing and related Services for Roadway Maintenance - Asphalt Package - 1 - 2025, UPIN 25103MF3MV01, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 25103MF3MV01; Job No. 25/0243

Vendor/Entity Legal Name (if applicable): Raba-Kistner, Inc.

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  0% - Non-Divisible

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Raba-Kistner Inc. in the amount of $197,337.00 for Professional Engineering Services regarding Construction Materials Testing and related Services for Roadway Maintenance - Asphalt Package - 1 - 2025, UPIN 25103MF3MV01, Precinct 3, Justification for 0% MWBE Participation Goal:  0% - Non-Divisible.

end

 

Background and Discussion:

 

Precinct 3 is requesting the Office of the County Engineer to enter into an agreement for professional engineering services to provide Construction Phase services for the subject maintenance project which consists of mill & overlay with base repairs on Spring Cypress Road and Louetta Road within Precinct 3. The total length of the project is 2.7 miles of roadway, covering the subject roads. Spring Cypress Road is a 4-lane (with cont. turn lane) asphalt major thoroughfare within 120-ft of ROW with 11-ft lanes, 1 concrete channel crossing over Spring Gully (VH-SPC16006) and open ditches. The corridor is on the HC road log. Louetta Road is a 4-lane (with cont. turn lane) asphalt major thoroughfare within 100-ft of ROW, with 11-ft lanes, 1 concrete channel crossing over Dry Gully (VH-LOU11005) and open ditches.

 

 

 

 

 

Expected Impact:

 

This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt and various other construction materials to ensure the material’s compliance with Harris County Engineering Department’s adopted standards and specifications as required by state law.

 

Alternative Options:

 

Construction materials testing is required by state law.  Thus, alternatives include issuing a purchase order for similar services to a different vendor or cancelling this construction project.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/09/2025

(25-0410) - 377

Approved Authorization to Negotiate

 

Location: Asphalt Package - 1 - 2025

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109

$

$197,337.00

$197,337.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$197,337.00

$197,337.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$197,337.00

$197,337.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 11/13/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer

 

Attachments (if applicable):