Legislation Details

File #: 26-0539    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 1/12/2026 In control: Commissioners Court
On agenda: 1/29/2026 Final action: 1/29/2026
Title: Request for approval of a Final Investment Memo for the Elevator Repair and Renovations Countywide projects for an incremental authorization of $11,020,252 for a total FY2026 authorization of $11,850,300, and a request for Commercial Paper funding for an additional amount of $3,355,000.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Managing Department: County Engineer

Managing Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Elevator Repair and Renovations Countywide

Project ID (if applicable): MF0ELEVATORS

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $11,020,252

Total Estimated Project Cost: $59,251,500 (FY 2026-30)

 

Request Summary:

title

Request for approval of a Final Investment Memo for the Elevator Repair and Renovations Countywide projects for an incremental authorization of $11,020,252 for a total FY2026 authorization of $11,850,300, and a request for Commercial Paper funding for an additional amount of $3,355,000.

end

 

 

 

 

Project Description:

This is a continuous lifecycle management project to identify and address all required upgrades and modernization of elevators, escalators, lifts, related equipment and infrastructure in County Facilities. This project addresses elevator equipment in multiple County facilities that are outdated and where replacement parts are not readily available and, in some cases, no longer available.                     

Below are the planned allocations; there might be changes in the County’s needs that result in minor operational and financial changes for the projects throughout the Fiscal Year, but overall scope will remain the same. Any additional authorization would go through Commissioners’ Court approval.

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

CIVIL COURTHOUSE ELEVATORS

$3,800K

FY2026

CIVIL COURTHOUSE ESCALATORS

$2,480K

FY2026

ANNEX 48 PARKING GARAGE

$400K

FY2026

ANNEX 48

$2,300K

FY2026

ANNEX 9

$200K

FY2026

ANNEX 14

$200K

FY2026

KATY LEADERSHIP ACADEMY

$250K

FY2026

YOUTH VILLAGE

$200K

FY2026

CONSTABLES OFFICE PCT 4

$250K

FY2026

CONSTABLES OFFICE, PCT 8

$193K

FY2026

EQUIPMENT/PARTS

$500K

FY2026

FY 2026 Authorization

$10,773K

 

Contingency 10%

$1,077K

 

FY 2026 Total Authorization

$11,850K

 

FY 2025 Carry Forward 

$(830)K

 

Total

$11,020K

 

 

Justification & Alternatives:

The County has a schedule to address elevator, escalator, lifts, and related systems deferred maintenance. Failure to continue maintaining the County's existing facilities may result in more expensive deferred maintenance, as well as the closure of certain areas, non-code compliance, and, most importantly, risks to life/safety. Elevators are linked to building fire alarm systems to ensure they operate properly during an event. Another elevator safety issue is people getting trapped in an elevator when they break down. Elevator entrapments or failures are a potential life safety issue. Elevators need to be modernized to avoid outages and entrapments. Modernized elevators increase the flow of employees and visitors throughout the facility, which is critical for efficient building operations. When elevators are out of service, it disrupts the building’s ability to maintain operations.

The Office of the County Engineer (OCE) continues to experience the effects of previous years’ inflation regarding materials and labor for construction projects.  Although inflation for costs of materials and labor is expected to increase at historical averages in FY2026, the increases from previous years are expected to remain.

 

Not funding this program would lead to an even greater backlog of deferred maintenance to perform later and, in some cases, could create hazards to life and safety. Delay in project timeline may increase costs due to increased deterioration of infrastructure, potential bid increases, and increase in material and labor costs.

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Previous Court Action:

Date

Agenda Item #

Action Taken

8/1/2017

4.d.3

$3M CP allocation

12/18/2018

1.s.1

$3.6M authorization

1/8/2019

4.i.3

$3.6M CP allocation

6/4/2019

CIP

$1M authorization in interim CIP

8/27/2019

4.e.7

$1M CP allocation

1/7/2020

II.1.c

$5M authorization in FY20 CIP

1/28/2020

4.g.2

$3M CP allocation

5/19/2020

4.f.3

$2M CP allocation

3/9/2021

88

Harris County - Proposed Capital Improvements Program; Facility and Maintenance Projects: Elevator Repair and Renovations Countywide, pages 281 and 287 ($1.35M authorization for FY21-22).

8/24/2021

94

$2,098,500 incremental authorization for FY21-22, $885K CP allocation.

3/8/2022

107

Request for approval of a Final Investment Memo for the Elevator Repair and Renovations Countywide project for an additional $2,838,000 for SFY 22 and request for approval of commercial paper funding for Engineering for the project in the additional amount of $1,185,000 (p.13).

10/18/2022

122

Request for approval of a Final Investment Memo for the Elevator Repair and Renovations Countywide project for an additional $981,000 for a FY 2023 authorization of $6,213,000. 22-6656.

8/29/2023

103

Request for approval of a Final Investment Memo for the Elevator Repair and Renovations Countywide project for an additional $7,190,000 for a FY24 authorization of $8,161,000.

9/19/2024

93.

Request for approval of a Final Investment Memo for the Elevator Repair and Renovations Countywide projects for an FY2025 authorization of $9,100,000.

10/29/2024

31

Request for approval of commercial paper funding for Engineering for the Elevator Repair and Renovations Countywide project in the additional amount of $1,150,000 for a total CP funding of $12,820,000. 

                     

Address: Multiple

Precinct(s): Countywide

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$3,355,000

$3,355,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$3,355,000

$3,355,000

$

Total Funding Request

$

$3,355,000

$3,355,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/29/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, Special Assistant County Attorney, 1/21/2026

Department Approval by: Samuel Peña- Chief of Infrastructure Services & Disaster Recovery

OMB CIP Team Approval by: Wanwei Tang, Analyst - Capital Projects and Infrastructure, 1/20/2026

Commercial Paper Request (For OMB use only):

Receiving Department: County Engineer

Project PeopleSoft ID: MF0ELEVATORS

CP Series Description: Commercial Paper Series D can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the Elevator Repair and Renovations Countywide project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.OMB Financial Management contact: Fahad Gulzar, Acting Deputy Executive Director, Office of Management and Budget