File #: 25-5141    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/13/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Request for approval of a change in contract with Environmental Allies Inc., in connection with Dowdell Woods Subdivision Drainage Improvements, with a deduction in the amount of $196,872.07, Job No. 24/0415-1, Grant Fund, UPIN 19103MF14A01, Precinct 3, MWBE Contracted Goal: 20.21%, MWBE Current Participation: 2.94%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0415, UPIN 19103MF14A01

Vendor/Entity Legal Name (if applicable): Environmental Allies Inc.

 

MWBE Contracted Goal (if applicable): 20.21%

MWBE Current Participation (if applicable): 2.94%

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Environmental Allies Inc., in connection with Dowdell Woods Subdivision Drainage Improvements, with a deduction in the amount of $196,872.07, Job No. 24/0415-1, Grant Fund, UPIN 19103MF14A01, Precinct 3, MWBE Contracted Goal: 20.21%, MWBE Current Participation: 2.94%.

end

 

Background and Discussion:

This project is in Northwest Harris County in both the White Oak Bayou and Cypress Creek watersheds. It is west of N. Eldridge Parkway and north of Cypress North Houston Road. The drainage system is currently roadside ditches. The proposed improvements are to regrade the roadside ditches, install a storm sewer system below the ditches, and connect to the K500-01-00 detention basin expansion project for mitigation on this project.

 

The change in contract includes the following:

 

The line items are adjusted to reconcile existing bid items, add new line item quantities to the project for completion of the proposed scope of work.

 

                     The decrease of existing bid Item quantities for line item numbers 16, 17, 18, 37, 38, 39, 40, 41 and 42 for a deduction in the amount of $933,673.34.

 

New Line Items:

 

                     Add a new line item “5 feet X 5 Feet Concrete Junction Box”, Unit of Measure Each, Unit Cost $10,000.00, Quantity 1 Each for an additional cost of $10,000.00.

                     Add a new line item “6 feet X 6 feet Concrete Junction Box”, Unit of Measure Each, Unit Cost $12,387.34, Quantity 2 Each for an additional cost of $24,774.68.

                     Add a new line item “7 feet X 4 feet Concrete Junction Box”, Unit of Measure Each, Unit Cost $17,887.73, Quantity 6 Each for an additional cost of $107,326.38.

                     Add a new line item “8 feet X 8 feet Concrete Junction Box”, Unit of Measure Each, Unit Cost $42,612.91, Quantity 1 Each for an additional cost of $42,612.91.

                     Add a new line item “10 feet X 5 feet Concrete Junction Box”, Unit of Measure Each, Unit Cost $43,569.80, Quantity 8 Each for an additional cost of $348,558.40.

                     Add a new line item “Fly ash for Subgrade treatment”, Unit of Measure Tons, Unit Cost $216.45, Quantity 425.15 Tons for an additional cost of $92,023.72.

                     Add a new line item “Lime/Fly ash Treatment (8-inch depth)”, Unit of Measure Square Yards, Unit Cost $6.75, Quantity 14,520 Square yards for an additional cost of $98,010.00.

 

The above additions and deductions result in a net change in the amount of ($196,872.07).

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Dowdell Woods subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/09/2025

348 (25-0210)

Transmittal - Advertisement

01/23/2025

162 (25-0502)

Contract Award - Environmental Allies, LLC

 

Location: Dowdell Woods Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Grant 2601

$

-$196,872.07

-$196,872.07

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$196,872.07

-$196,872.07

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$196,872.07

-$196,872.07

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/7/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC)