File #: 25-4484    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/17/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval of an amendment to an agreement with WSB, LLC in the amount of $37,865.00 for Professional Engineering and related services in connection with Asphalt Rehabilitation - Memorial Drive between Greenbay Street and West of Chimney Rock - 2024, UPIN 25103MF3MT01, Asphalt Rehabilitation - Campbell Road - 2025, UPIN 25103MF3N001, Precinct 3.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN - 25103MF3MT01

Vendor/Entity Legal Name (if applicable): WSB, LLC

 

MWBE Contracted Goal (if applicable): 0%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  0% - Non-Divisible

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with WSB, LLC in the amount of $37,865.00 for Professional Engineering and related services in connection with Asphalt Rehabilitation - Memorial Drive between Greenbay Street and West of Chimney Rock - 2024, UPIN 25103MF3MT01, Asphalt Rehabilitation - Campbell Road - 2025, UPIN 25103MF3N001, Precinct 3.

end

 

Background and Discussion:

 

Precinct 3 is requesting the Office of the County Engineer to approve an amendment for additional professional engineering services to provide traffic control design for the full reconstruction portion of Campbell Road within Precinct 3. The total lengths of the projects are 1.7 miles and 1.5 miles, covering the subject roads.

 

Expected Impact:

 

The maintenance project will improve the road quality for the community in the specified area.

 

Alternative Options:

 

Without this project the road cannot be maintained properly. The goal is to provide better mobility and/or eliminate hazards from the roadway as requested by the Precinct.

 

 

County Strategic Plan Goal:  1. Make Harris County safer and more just.

County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

10/29/2024

132 (24-6619)

Request for approval to negotiate with WSB LLC for Professional Engineering and related services in connection with Asphalt Rehabilitation - Campbell Road - 2025, UPIN 25103MF3N001, Precinct 3.

2/27/2025

19 (25-1166)

Request for approval to execute an agreement with WSB, LLC in the amount of $177,705.20 for Professional Engineering and related services in connection with Asphalt Rehabilitation - Memorial Drive between Greenbay Street and West of Chimney Rock - 2024, and Asphalt Rehabilitation - Campbell Road - 2025, UPINs 25103MF3MT01 & 25103MF3N001, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.

 

Location:

Address (if applicable): Campbell Road, between Clay rd. and Hempstead Hwy, spanning approx. 1.5 miles.

Houston, TX 77041

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109

$

$ 37,865.00

$ 37,865.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$ 37,865.00

$ 37,865.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$ 37,865.00

$ 37,865.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/7/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer.

 

Attachments (if applicable): Contract exhibits and Agreement.