Harris County Logo
File #: 24-0863    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 2/12/2024 In control: Commissioners Court
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Request for approval of a change in contract with Yellowstone Landscape Central, Inc., in connection with final On-Call - Maintenance - Mowing East Aldine Camp - 2021, with a deduction in the amount of $516,434.94, Job No. 21/0187-2, UPIN 22102MF26C01, Precinct 2, MWDBE Contracted Goal: 11%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No: Job No. 21/0187

Vendor/Entity Legal Name (if applicable): Yellowstone Landscape Central, Inc.

 

MWDBE Contracted Goal (if applicable): 11%

MWDBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Yellowstone Landscape Central, Inc., in connection with final On-Call - Maintenance - Mowing East Aldine Camp - 2021, with a deduction in the amount of $516,434.94, Job No. 21/0187-2, UPIN 22102MF26C01, Precinct 2, MWDBE Contracted Goal:  11%.

end

 

Background and Discussion:

Project includes mowing services in East Aldine Camp.  The terms of services in connection with purchase order HCNTY-0000063600 is being closed at the request of the Precinct, and in accordance with the recommendation of Harris County Engineering Department.

 

Expected Impact:

The change allows the unused funds to be returned to the Precinct. 

 

Alternative Options:

Continue with the project in accordance with the original scope.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing                     

_ Public Health

x Transportation

_ Flooding

x Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/02/2022

177

Contract Renewal

08/29/2023

48

Contract Amendment for additional funds

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

-$516,434.94

-$516,434.94

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

-$516,434.94

-$516,434.94

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

-$516,434.94

-$516,434.94

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: February 27, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department

 

Attachments (if applicable): County Auditor’s Form 1258B