File #: 25-2137    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 3/25/2025 In control: Commissioners Court
On agenda: 4/10/2025 Final action: 4/10/2025
Title: Request for approval of a Final Investment Memo for the Harris County Sheriff's Office Complex at 5910 Navigation project, for an additional incremental authorization of $138,139,539 for a total authorization of $157,039,539.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP

Managing Department: County Engineer

Managing Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Harris County Sheriff’s Office Complex Relocation and Consolidation at 5910 Navigation

Project ID (if applicable): MF0TW

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): 14.96%

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $138,139,539

Total Estimated Project Cost: $157,039,539

 

Request Summary:

title

Request for approval of a Final Investment Memo for the Harris County Sheriff’s Office Complex at 5910 Navigation project, for an additional incremental authorization of $138,139,539 for a total authorization of $157,039,539.

end

 

 

 

Project Description:

The new HCSO complex will house a new state-of-the-art Property/Evidence Facility with Vehicle Processing, Investigation/Administration building, Community Center, and parking garage. As a result of the space requirement, an Urban Farm, previously located on site, will be moved to a nearby location.

Project Scope:

In 2021, RDLR was selected through an RFQ process to provide architectural, engineering, and community outreach services for improvements to Harris County Sheriff’s Office.   RDLR completed program verification and has started the design of the Harris County Sheriff’s Office Complex located on an approximately 7-acre tract of land at 5910 Navigation.   The overall objective for consolidating HCSO operations is to increase productivity and department efficiency.

During Phase 1, the prior programming phases, several community events were hosted to uncover project needs.  These needs included 4 facilities, HCSO Investigations building, HCSO Property and Evidence Building, a community center and a parking garage.  This information was taken into Phase 2 the planning, programming and design phase.

To develop the planning in Phase 2, a series of workshops were hosted which included HCSO command and staff, Commissioner Precinct 2, and the Precinct 2 community.  This resulted in the building and site designed to be a harbor of safety for HCSO.  The goal is to provide a space that increases work efficiency and productivity through planning and design. 

Phases 3 and 4 will include the demolition of the existing site and the construction of the new site. The new HCSO Complex will encompass:

1.                     an approximately 75,780 sf, 4-story Investigations Building,

2.                     an approximately 80,725 sf, 2-story Property/Evidence and CSI Building with Vehicle Processing

3.                     an approximately 12,440 sf, 2-story community center and

4.                     a new 3-4 story, 400 car Parking Garage with public parking on the ground level and a secured ramp and secured parking above ground level for HCSO.

The new HCSO Complex will consolidate the Criminal Investigations Bureau (CIB) onto one complex.  This will provide a safe haven in the community and will help build community relationships with law enforcement. This will affect approximately 330 to 385 current employees and replace aging, outdated infrastructure. 

Scope changes:

Since the approval of the Phase 2 Preliminary Investment Memo (PIM), there have been a few changes within CIB which are reflected in design. Criminal Warrants has added two new units - Violent Person Task Force (VIPER) and Crime Victims Assistance Unit (VICAT), Homicide has added a squad, and Crime Scene Investigations added vehicle processing.

Phase 3 abatement and demolition of existing structures onsite, as well as backfill, and finish grade requirements at 5910 Navigation for the new Harris County Sheriff’s Office Complex have been completed. The site is now ready for construction to begin.

Current Investment Memo Request (Request this FIM)

The next phase, Phase 4, of the project includes the construction of new facilities to house the Criminal Investigations Bureau and Property and Evidence. This phase will also include any additional construction support, IT installation, security, audio visual requirements, furniture, fixtures and equipment, fees for authorities having jurisdiction, utility connection fees, and contingency.

Expected Impact:

The overall purpose of the project is to bring all the HCSO Criminal Investigations Bureau (CIB) together under one roof, thereby, reducing costs, increasing productivity, improving customer service.

Currently, the Criminal Investigations Bureau is spread out across Harris County in various buildings.  Geographically, work performed by various disciplines requires travel to multiple areas to complete one task.  Crime Scene Units often travel to various locations to process evidence, submit evidence, and complete reports.  Investigators who interact with Crime Scene Units and Warrant personnel face similar inefficiencies.  Best practices indicate that housing all of the Criminal Investigation Bureau in one location will streamline the work process, saving time and money.  Productivity would increase as travel time is minimized.  The public would also be better served by going to one place to participate in investigative needs.

 

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

PHASE 1: (Previously Approved and Expended) Property Acquisition and Pre-Design

$5,800,000

COMPLETE

PHASE 2: (Previously approved PIM) Planning, Program Verification and Design

$10,400,000

COMPLETE

PHASE 3: (Previously approved FIM) Abatement and Demolition

$2,700,000

COMPLETE

PHASE 4: (For approval in this FIM) Estimated Future Construction Cost

$137,389,539

Q4 2026

PHASE 4: (For approval in this FIM) Installation of Industrial Kitchen in Community Center building, funded by Harris County Precinct 2.

$750,000

Q4 2026

Total

$157,039,539

Q4 2026

 

OMB will transfer $25,000,000 in Certificates of Obligation, Series 2024 budget to the Harris County Engineering Department for this project and will return to Commissioners Court with subsequent transfers.

Justification & Alternatives:

If this FIM is not approved, the construction of the Harris County Sheriff’s Office Complex cannot begin. This will cause delays in the current project schedule and the construction cost of a new facility will continue to rise. Locating an affordable existing facility to retrofit appropriately for an investigative arm of a law enforcement agency is unlikely. In addition, the Criminal Investigation Bureau of the 3rd largest Sheriff’s Office in the nation would continue to operate in an inefficient, substandard fashion.  Investigative costs would continue to be high with less than acceptable productive results as investigators are required to travel to multiple locations to complete a task.  The infrastructure of the facility would continue to fail, and maintenance costs would continue to rise. 

In addition, Criminal Warrants Unit and Crime Scene Unit would be displaced.  These units, which were previously located in a soon to be demolished, leased space, have been temporarily located.  They do not have a permanent home.

 

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  1. Make Harris County safer and more just.

County Strategic Plan Objective: E: Increase efficiency across the legal system.

Justice/Safety Initiative (Goal 1):  A2: Apply “Crime Prevention Through Environmental Design” principles to improve built environments of neighborhoods and increase safety.

Infrastructure Initiative (Goal 2):  H4: Consistently embed sustainability considerations in the project planning and design process.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): R3: Strengthen the County’s emergency response function.

Housing Initiative (Goal 6): N/A


Decision Analysis Matrix Score (rubric on last page): 13

Previous Court Action:

Date

Agenda Item #

Action Taken

07/11/2017

1.a.1

Approval - Authorize the purchase of Tract 1 for $4,902,428, $202,428 over the appraised value, for the Sheriff's Office replacement facility at 5910 Navigation. Note HCED closed on property 6 Sept 2017

08/01/2017

4.d.6

Approval - Sheriff's Office Facility at 5910 Navigation project for initial funding in the amount of $7million.

09/12/2017

1.b.1

Approval - Authorize to Negotiate with InControl Technologies, Inc., for environmental services for 5910 Navigation Boulevard in support of the property being placed into the Voluntary Cleanup Program with the Texas Commission on Environmental Quality.

07/10/2018

1.f.1-7

Approval - Huitt-Zollars to perform Professional Architecture and Engineering Services for improvements to 5910 Navigation Boulevard. $188,920.00

06/04/2019

1.f.1

Approval - Amendment for Huitt-Zollars, Inc to perform additional architecture and engineering services for improvements to 5910 Navigation Boulevard in Precinct 2. $68,180

06/30/2020

1.o

No Action - 5910 Navigation programming and site utilization plan, and authorization for the Budget Office to allocate funding in an amount not to exceed $79 million for design and construction of the project.

07/14/2020

1.o

Approval - 5910 Navigation programming and site utilization plan that includes the relocation and consolidation of various Sheriff’s Office operations: authorization to work with appropriate stakeholders to evaluate the inclusion of a consolidated city/county property evidence facility as part of the project, and for the Budget Office to allocate funding for the design and construction of the project. The Budget Office shall allocate and process any necessary budget transfers in an amount not to exceed $79 million dollars. The Office of the County Engineer shall proceed with design and shall work with the Purchasing Agent to advertise for a Construction Manager at Risk (CMAR).There shall be a community engagement process for community space within the project. The Lockwood facility shall not be reconstituted into a law enforcement facility.

08/11/2020

1.g.1

Item Held - Amendment No 2 for Professional Architecture and Engineering Services along with Community Outreach Services for improvements to 5910 Navigation Boulevard, UPIN 18035MF0UB01, Precinct 2 Original: $188,920.00 - 07/10/2018 (Approved) Amend 1: $68,120.00 - 06/04/2019 (Approved) Amend 2: $6,915,000.00 - 08/11/2020 (Item Held ‘Not Approved’)

8/11/2020

4.c.1

Item Held - Request for approval of commercial paper funding for: The Office of the County Engineer for the HCSO facility at 5910 Navigation project in the additional amount of $7 million for a total CP funding of $14 million.

8/25/2020

22.c.4

Approved - Publish a request for qualifications in conjunction with the Purchasing Agent for architecture, engineering, and community outreach services for improvements to the Harris County Sheriff’s Office facility at 5910 Navigation Boulevard in Precinct 2; and resubmission of Budget Management item 4.c.1. from the August 11, 2020, commercial paper funding for the Office of the County Engineer for the HCSO facility at 5910 Navigation project in the additional amount of $7 million for a total CP funding of $14 million.

2/26/2021

284

Approved - Request for approval of RDLR Architects Inc. for architectural and/or engineering services for design and construction of the HC Sheriff’s Office Complex

6/29/2021

406

Approved - Award w/ RDLR Architect, Inc. in the amount of $310,844 for professional architectural and/or Engineering services for design and construction of the Sheriff’s Office Complex, program re-verification (200272)

4/5/2022

114

Approved - Preliminary Investment Memo for the Design of the Harris County Sheriff’s Office Complex Relocation and Consolidation at 5910 Navigation project for $10,400,000 for design for a total of $16,200,000 and request for approval of commercial paper funding for Engineering for the project in the additional amount of $1,005,000 for a total of $15,005,000.

6/14/2022

229

Approved - Project scheduled for advertisement for construction manager at risk for the New Sheriff’s Office Complex located at 5910 Navigation Boulevard for the Office of the County Engineer (220168).

1/10/2023

230

Approved - award on the basis of highest overall evaluation with Durotech Inc. for construction manager at risk for the new Sheriff’s Office complex located at 5910 Navigation Boulevard for the Office of the County Engineer and the county, at its sole discretion, may discontinue negotiations and proceed to negotiate with the next ranking offer if unable to agree to an executable contract (220168), MWDBE Contracted Goal: 20%.

5/16/2023

291

Approved - the County Judge execute an agreement with Durotech Inc. in the amount of $166,000 for construction manager at risk for the new Sheriff’s Office Complex located at 5910 Navigation Boulevard for the Office of the County Engineer in connection with an award approved by Commissioners Court on January 10, 2023 (220168), MWDBE Contracted Goal: 20%.

6/6/2023

266

Approved - Payment and Performance bonds from Durotech Inc. for construction manager at risk for the new Sheriff’s Office complex located at 5910 Navigation Boulevard for the Office of the County Engineer, in connection with an agreement approved by Commissioners Court on May 16, 2023 (220168), MWDBE Contracted Goal: 20%.

6/4/2024

489

Request by the Office of the Purchasing Agent that the County Judge execute an agreement with Durotech, Inc. in the amount of $2,305,689 for the guaranteed maximum price for Construction Manager at Risk for the new Sheriff’s Office complex located at 5910 Navigation Boulevard for the Office of the County Engineer (PTO 1) in connection with an award approved by Commissioners Court on May 16, 2023, and for the County Clerk to execute any applicable bonds to be received (220168), MWDBE Contracted Goal: 21.94%.

 

Address: 5910 Navigation Blvd, Houston, TX 77011

Precinct(s): Precinct 2

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Other

$

$750,000

$750,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$750,000

$750,000

$

Additional Budget Request

 

Certificate of Obligation

$

$25,000,000

$25,000,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$25,000,000

$25,000,000

$

Total Funding Request

$

$25,750,000

$25,750,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 4/10/2025

Anticipated Implementation Date (if different from Court date): 4/10/2025

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Legal funding compliance confirmed by: Paige Abernathy, Assistant County Attorney, 3/18/2025

Department Approval by: Dr. Ronald L. Lerner, DBA, MScE., IAEng, LSSBB

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 3/19/2025

________________________________________

Commercial Paper Request (For OMB use only):

Receiving Department: N/A

Project PeopleSoft ID: N/A

CP Series Description: N/A

OMB Financial Management contact: N/A

Decision Analysis Matrix scoring tool - Commissioners Court has approved the rubric below for scoring capital projects. Please complete the last two rows for OMB review.

Scoring option

Strategic Plan alignment (3x weighting)

Evidence base

Impact on outcomes

Cost effectiveness

Ease of implementation

Collaboration / partnerships

Environmental sustainability

Equity

Total

-1

Antithetical to one or more aspects of the Strategic Plan

Evidence shows net negative impact on the intended goal

Impact is clearly negative

Costs expected (or shown) to outweigh benefits

County has no/limited existing capabilities and dependencies are likely to impede

Could negatively impact relationships with partners

Negatively impacts environment and/or climate change mitigation efforts

Inequitable

n/a

0

Does not align to a Strategic Objective

Evidence base is not well defined or measurable

Size of impact on one or more strategic outcomes is negligible or unclear

Net comparison is unclear

County has no/limited existing capabilities or dependencies are likely to impede

Does not involve collaboration with partners

Net neutral impact on environment and/or climate change mitigation efforts

Does not consider equity to a meaningful degree

n/a

1

Aligns to a Strategic Objective but not to a Strategic Initiative

Limited evidence-based research on outcomes; may have qualitative/theoretical support

Outcomes are defined but without target levels and/or expected impact is moderate

Moderate direct/indirect benefit relative to costs

County has existing capability to implement, or dependencies are unlikely to impede

Moderately expands County leverage through collaboration with partner(s)

Marginally positive impact on environment and/or climate change mitigation efforts

Considers equity to a meaningful degree, but not comprehensively

n/a

2

Aligns to a Strategic Objective and a Strategic Initiative

Outcomes are directly supported by evidence base or credible research supports anticipated outcomes

Outcomes are clearly defined and include target levels; expected impact on outcomes is high

Significant direct/indirect benefit relative to costs

County has existing capability to implement, and dependencies are unlikely to impede

Significantly expands County leverage through collaboration with partner(s)

Positively impacts environment and/or climate change mitigation efforts

Considers equity meaningfully and comprehensively

n/a

Score    (-1,0,1,2)

(2*3) =6

1

1

2

1

0

1

1

13

Rationale

Meets county strategic plan goal to “Make Harris County safer and more just”

Limited evidence supports impact. More efficient use of HCSO resources.

No study done to quantify exact impact, but outcomes will be affected in positive.

New facility will improve total efficiency of HCSO.

Funding has already been previously reviewed and earmarked.

Doesn’t involve collaboration with partners.

Building design meets LEED criteria.

Has a MWBE participation requirement.

n/a