Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0230, UPIN 23104MF2PP01
Vendor/Entity Legal Name (if applicable): Main Lane Industries, Ltd.
MWDBE Contracted Goal (if applicable): 32%
MWDBE Current Participation (if applicable): 22.75%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Main Lane Industries, LTD, in connection with Intersection Improvement - Katy Hockley Road at Clay Road - 2022, adding 150 calendar days, Job No. 22/0230-2, UPIN 23104MF2PP01, Precinct 4, MWDBE Contracted Goal: 32%, MWDBE Current Participation: 22.75%.
end
Background and Discussion:
This project is for the intersection improvements and roadway widening at Clay and Katy Hockley - Harris County Precinct 4.
Added items :
PCO #3 Time extension request - 150 Days
Expected Impact:
Changes allows for the addition of calendar days to the contract so the project can be completed in accordance with the original intent.
PCO #3 - Change allows to extend the contract time while conflict with Kinder Morgan pipelines is being resolved.
Alternative Options:
Revise original scope.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
09/13/2022 |
275 |
Contract Award |
|
04/23/2024 |
TBD |
Contract Amendment for additional funds and extension of project term |
Location:
Address (if applicable):
Precinct(s): Precinct 4
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: May 07, 2024
Anticipated Implementation Date (if different from Court date): n/a
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): County Auditor’s Form 1258B