Legislation Details

File #: 25-0089    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/22/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval of a change in contract with Frost Construction Co Inc., in connection with Deussen Park Maintenance Barn Renovation - 2022, with an addition in the amount of $23,095.85, Job No. 23/0435-3, UPIN 22101MF26401, Precinct 1, MWBE Contracted Goal: 20%, MWBE Current Participation: 18.01%.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Dr. Milton Rahman, Ph.D, P.E, PMP, CFM, ENV-SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official:

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 23/0435

Vendor/Entity Legal Name (if applicable): Frost Construction Co. Inc

 

MWBE Contracted Goal (if applicable): 20%

MWBE Current Participation (if applicable): 18.01%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Frost Construction Co Inc., in connection with Deussen Park Maintenance Barn Renovation - 2022, with an addition in the amount of $23,095.85, Job No. 23/0435-3, UPIN 22101MF26401, Precinct 1, MWBE Contracted Goal: 20%, MWBE Current Participation: 18.01%.

end

 

Background and Discussion:

Existing parks maintenance facility consisting of two (2) steel buildings on concrete pads erected in about 1970’s. One of the buildings has severe deterioration to the structural framing occurring at the base of the rigid steel frame. Existing office staff amenities of breakroom and restrooms are outdated and in poor condition. Asbestos has been identified in the facility and needs to be addressed. The site condition has ponding issues with stagnate water after rainfall.

 

Changes included here involve: Adding electrical motors to newly installed overhead doors at the facility, per Owner request. This feature was not originally included in the project’s base bid.

 

Expected Impact:

These changes allow the contractor to bill for required changes resulting from unforeseen conditions and Owner Requests.

 

Alternative Options:

Should we not move forward with this change in contract, these items will remain unreconciled delaying the closeout of the contract and project.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/14/23

283

Advertisement of Project Approved

12/19/23

276

Contract - Award

06/04/24

73

Request for approval of a change in contract with Frost Construction Company, Inc. in connection with Maintenance Barn at Deussen Park - Renovation - 2022, adding 16 calendar days, with an addition in the amount of $79,598.36, Job No. 23/0435, UPIN 22101MF26401, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 20%

10/8/24

63

Request for approval of a change in contract with Frost Construction Co Inc., in connection with the Deussen Park Maintenance Barn Renovation project, in the amount of $26,717.55 and 2 calendar days. Job No. 23/0435, UPIN 22101MF26401, Precinct 1, MWDBE Contracted Goal 20%, MWDBE Current Participation 20%

 

 

 

 

Location:

Address (if applicable): 12303 Sonnier St. #Bldg M, Houston, TX 77044

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$23.095.85

$23.095.85

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$23.095.85

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$23.095.85

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/9/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department:

Truitt Rounsavall, PE, MBA, PMP, LSSBB; Interim Director - HCED Vertical Construction - Engineering Group

Jesus A. Venegas; PM - Construction, HCED Vertical Construction - Engineering Group

 

Attachments (if applicable): County Auditor’s Form 1258B (Job No. 23/0435-3)