File #: 24-4097    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/2/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval of a change in contract with Traf-Tex, Inc., in connection with final construction of Traffic Signal - Kieth Harrow at Old Greenhouse - 2021, adding 90 calendar days, with an addition in the amount of $308.08, Job No. 21/0369-1, UPIN 22104MF2FV01, Precinct 4, MWDBE Contracted Goal: 17.50%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0369, UPIN 22104MF2FV01

Vendor/Entity Legal Name (if applicable): Traf-Tex, Inc.

 

MWDBE Contracted Goal (if applicable): 17.50%

MWDBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Traf-Tex, Inc., in connection with final construction of Traffic Signal - Kieth Harrow at Old Greenhouse - 2021, adding 90 calendar days, with an addition in the amount of $308.08, Job No. 21/0369-1, UPIN 22104MF2FV01, Precinct 4, MWDBE Contracted Goal: 17.50%.

end

 

Background and Discussion:

The project consists of the construction of a temporary traffic signal system at the intersection of Kieth Harrow at Old Greenhouse Road.  Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.  Added items:

-                     PCO - 1 To add 90 days for acquisition and installation of Type D electrical box.

-                     PCO - 2 Final Adjustments - $308.08

 

Expected Impact:

Changes allow for compensation to the Contractor of the actual quantities used in construction, in accordance with the original intent of the project and in compliance with precinct requests.

 

Alternative Options:

Revise original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X_ Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/04/2022

22-0084

Contract Award

 

Location:

Address (if applicable):

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$308.08

$308.08

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$308.08

$308.08

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$308.08

$308.08

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: July 15, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B