Title: Request for approval of an amendment to an agreement with Vogler & Spencer Engineering, Inc., in the amount of $70,400.00 to prepare metes & bounds descriptions in connection with Cutten Rd - from south of Bavaria Dr to Cossey Rd - 2019, UPIN 20104MF1C801, Precinct 3, MWBE Contracted Goal: 2.05%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: Commissioner, Precinct 3

Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN - 20104MF1C801

Vendor/Entity Legal Name (if applicable): Vogler & Spencer Engineering, Inc.

 

MWBE Contracted Goal (if applicable): 2.05%

MWBE Current Participation (if applicable):

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with Vogler & Spencer Engineering, Inc., in the amount of $70,400.00 to prepare metes & bounds descriptions in connection with Cutten Rd - from south of Bavaria Dr to Cossey Rd - 2019, UPIN 20104MF1C801, Precinct 3, MWBE Contracted Goal: 2.05%.

end

 

Background and Discussion:

 

Precinct 3 is requesting the Office of the County Engineer to enter into an amendment for professional engineering services to provide additional metes and bounds for the right of acquisition and temporary construction easements.  The Cutten Rd project general scope is design and construction of a standard four (4) lane concrete boulevard extension of Cutten Rd from 270-ft north of Magnolia Dr. to Cossey Rd. in 100-ft right of way with 32-ft raised medians and underground storm sewer.

 

Expected Impact:

 

 This action will allow the firm to perform the necessary metes & bounds Survey for remaining 20 tracks.

 

Alternative Options:

The alternative is to not include the additional acquisitions, but the project would not be able to be constructed.

County Strategic Plan Goal:  1. Make Harris County safer and more just.

County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/10/2021

102

Recommendation that the County Judge execute an agreement with Vogler & Spencer Engineering, Inc. in the amount of $454,124.58 and an approval of funds not to exceed $723,611.54 for Professional Engineering Services for improvements to Cutten Road from south of Bavaria Drive to Cossey Road, UPIN 20104MF1C801, Precinct 4.

11/15/2022

51

Request for approval to execute an amendment with Vogler & Spencer Engineering, Inc. in the amount of $78,117.00 for Professional Engineering Services to provide improvements to Cutten Road from south of Bavaria Drive to Cossey Road, UPIN 20104MF1C801, Precinct 3 (project was awarded prior to launch of County’s M/WBE Program).

09/19/2023

60

Request for approval to execute an amendment with Vogler & Spencer Engineering, Inc. in the amount of $21,979.37 for Professional Engineering Services to provide improvements to Cutten Road from south of Bavaria Drive to Cossey Road, Precinct 3 (project was awarded prior to launch of County’s M/WBE Program).

1/8/2026

52

Request for approval of an amendment to an agreement with Vogler & Spencer Engineering, Inc. in the amount of $123,149.00 for Professional Engineering and related services in connection with Cutten Rd - from south of Bavaria Dr to Cossey Rd - 2019, UPIN 20104MF1C801, Precinct 3, MWBE Contracted Goal: 2.05%.

7/30/26

24

Request for approval of an amendment to an agreement with Vogler & Spencer Engineering, Inc. in the amount of $23,320.00, for Professional Engineering and related services in connection with Cutten Rd - from south of Bavaria Dr to Cossey Rd - 2019, UPIN 20104MF1C801, Precinct 3, MWBE Contracted Goal: 2.05%.

 

Location: Cutten Rd From south of Bavaria Dr to Cossey Rd.

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Road

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$70,400.00

$70,400.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$70,400.00

$70,400.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$70,400.00

$70,400.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 11/19/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Contract & Exhibits