File #: 24-4098    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/2/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval of a change in contract with Allgood Construction Co., Inc. in connection with final construction of Tidwell Road from West of Greens Bayou to CE King Parkway, adding 515 calendar days, with a deduction in the amount of $138,104.45, Job No. 19/0305-4, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 19/0305, UPIN 16101MF0H401

Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Allgood Construction Co., Inc. in connection with final construction of Tidwell Road from West of Greens Bayou to CE King Parkway, adding 515 calendar days, with a deduction in the amount of $138,104.45, Job No. 19/0305-4, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

Background and Discussion:

Project includes the construction of 4-Lane Concrete Boulevard and a new bridge at Greens Bayou.  The roadway pavement had been constructed and used long before the new bridge completion.  The work changes are the following:

•                     Relocation of Inlet at Station 12+25 LT in the additional amount of $3,500.00 and an additional 10 days.

•                     Construction to re-stripe the existing asphalt from the transition on the west of the project towards the west with $0.00 and additional 1 day.

•                     To refresh striping and buttons between John Ralston and CE King that was previously placed when traffic was opened to 4 lanes with $0.00 and additional 1 day.

•                     Requesting additional days due to the following: Tropical Storm Beta, RFI#018, RFI#009, RFI#003 and delay due to material and trucking shortage during bridge construction. with $0.00 and additional 198 days.

•                     Final Adjustments in the amount (deduction) of -$141,604.45 with zero days.

•                     Contractor (Allgood) is requesting additional days due to Voiding CO 02, 03, and CO 06 - with $0.00 and additional 305 days.

•                     Total Amount Change (deduction) is -$138,104.45 and a total of 515 days.

 

 

Expected Impact:

The new pavement marking will better serve the public traffic.  The inlet relocation will improve the local drainage and provide the safer condition to the nearby sidewalk and bus station.

 

Alternative Options:

Maintain the original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing                     

_ Public Health

x Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

10/29/2019

20.c.9.b

Contract Award

12/01/2020

1.k.2

Contract Amendment for additional funds and extension of project term

05/16/2023

23-2880

Contract Amendment for additional funds and extension of project term

11/14/2023

23-6821

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

-$138,104.45

-$138,104.45

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

-$138,104.45

-$138,104.45

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

-$138,104.45

-$138,104.45

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date:  July 15, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B