Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): Job No. 23/0074, UPIN 19104MF13401
Vendor/Entity Legal Name (if applicable): Specialty Construction TX, LLC
MWBE Contracted Goal (if applicable): 27%
MWBE Current Participation (if applicable): 10.35%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, Job No. 23/0074, UPIN 19104MF13401, Precinct 2, MWBE Contracted Goal: 27%, MWBE Current Participation: 10.35%.
end
Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date is important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.
Expected Impact:
N/A
Alternative Options:
N/A
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H6: Expand neighborhood drainage programs.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
03/14/2023 |
371 (23-1455) |
Transmittal - Advertisement |
|
05/16/2023 |
266 (23-2912) |
Award - Construction Contract - Specialty Construction TX, LLC |
|
04/23/2024 |
66 (24-2186) |
Contract Amendment (23/0074-1) for additional funds and extension of project term |
|
06/04/2024 |
80 (24-3295) |
Contract Amendment (23/0074-2) for additional funds and extension of project term |
|
07/15/2024 |
68 (24-4056) |
Contract Amendment (23/0074-3) for extension of project term |
|
11/12/2024 |
70 (24-7214) |
Contract Amendment (23/0074-4) for additional funds and extension of project term |
|
12/10/2024 |
102 (24-7496) |
Contract Amendment (23/0074-5) for extension of project term |
Location: Fallbrook, Ridgepoint and Westpoint Subdivisions, Fallbrook, Texas
Address (if applicable): N/A
Precinct(s): Precinct 2
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$ |
$ |
$ |
|
Grants - Proposed Budget (To be filled out by Grants staff only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 1/23/2025
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer
Attachments (if applicable): Certificate of Substantial Completion