Legislation Details

File #: 26-3615    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 5/28/2026 In control: Commissioners Court
On agenda: 6/11/2026 Final action: 6/11/2026
Title: Request for approval to execute an interlocal agreement with M&M Gosling Express, Inc. to construct improvements in and around 17008 Telge Road (Telge Rd Segment 5 - from 1,780-ft North of Telge Ranch Rd to 300-ft North of Grant Rd) for the future M&M Gosling development of which improvements include constructing a left turn lane in the public right-of-way, UPIN 23103MF2QF01, Precinct 3.
Attachments: 1. 26-3615-ILA-23103MF2QF01-Telge Rd Segment 5-MandM-6.11.26 Agmt

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: Commissioner, Precinct 3

Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

 

Project ID (if applicable): UPIN 23103MF2QF01

Vendor/Entity Legal Name (if applicable): M&M Gosling Express, Inc.

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  Exempt - Interlocal/Cooperative Agreement

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title
Request for approval to execute an interlocal agreement with M&M Gosling Express, Inc. to construct improvements in and around 17008 Telge Road (Telge Rd Segment 5 - from 1,780-ft North of Telge Ranch Rd to 300-ft North of Grant Rd) for the future M&M Gosling development of which improvements include constructing a left turn lane in the public right-of-way, UPIN 23103MF2QF01, Precinct 3.

end

 

Background and Discussion:

The traffic impact analysis for the M&M Gosling Express Inc. development at 17008 Telge Road requires a southbound left turn lane. The interlocal agreement will allow the developer to defer the required construction of the left turn lane which will be constructed by Harris County under the Telge Road expansion project.

 

Expected Impact:

The interlocal agreement will result in a cooperative arrangement between Harris County and M&M Gosling Express Inc.

 

Alternative Options:

An alternative would be to not enter into a cooperative agreement which will result in less than an optimal situation as the M&M Gosling Express Inc. would construct the left turn lane at considerable expense, only for it to be removed by the Harris County road expansion project at additional unnecessary cost.

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): 17008 Telge Road

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$61,278.10

$61,278.10

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$61,278.10

$61,278.10

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$61,278.10

$61,278.10

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/11/2026

 

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Lauren Valdes-Assistant Director - Contracts & Procurement

Engineering

Attachments (if applicable): Interlocal Agreement and Exhibits