Legislation Details

File #: 24-2753    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 4/25/2024 In control: Commissioners Court
On agenda: 5/7/2024 Final action: 5/7/2024
Title: Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Sidewalk & Bikeway - El Camino & El Rio Street - 2020, adding 429 calendar days, with an addition in the amount of $169,326.08, Job No. 22/0001-2, UPIN 20101MF1JH01, Precinct 1, MWDBE Contracted Goal: 18%, MWDBE Current Participation: 24.81%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0001, UPIN 20101MF1JH01

Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC

 

MWDBE Contracted Goal (if applicable): 18%

MWDBE Current Participation (if applicable): 24.81%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Sidewalk & Bikeway - El Camino & El Rio Street - 2020, adding 429 calendar days, with an addition in the amount of $169,326.08, Job No. 22/0001-2, UPIN 20101MF1JH01, Precinct 1, MWDBE Contracted Goal: 18%, MWDBE Current Participation: 24.81%.

end

 

Background and Discussion:

Project includes the installation of bike lanes and the construction of a 6-foot-wide concrete sidewalk on each

side of El Camino Street and El Rio Street from Holly Hall Street to El Rio Street.

Change includes:

* Additional Pre-Cast Concrete Bikeway Curb (6” x 14”) at 3 locations, amount is $1,080.00 and 0 Days.

* Removal of existing stripe ceramic buttons located at new tire path, amount is $3,926.00 and 3 Days.

* Additional days needed due to lead time ordering on the Green Type C, Additional 115 Days with $0 amount.

* Industry wide material price increase on Item#14- 6” path, amount is $4,589.95 and 0 Days.

* Price escalation of payment on Item #13, 4.5 Sidewalk, amount is $5,504.28 and 0 Days.

* Price escalation of payment on Item #12, 10” H.E strength driveway, amount is $11,531.71 and 0 Days.

* Additional Days due to scope of work changes, added 311 Days.

* Several pay items at the beginning of the project that were changed-added quantities, amount is $114,503.14 and 0 Days.

* Final Cost Adjustment in the amount of $28,191.00 and 0 Days.

* Total Change Amount is $169,326.08 and additional of 429 Days.

 

Expected Impact:

Change allows for the contractor to complete additional work required to accommodate field conditions and

the requests of the Precinct while maintaining the overall original intent of the project.

 

 

 

Alternative Options:

Reduce the scope of work to include only areas where field conditions do not require changes to the original

design and estimated quantities.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing                     

_ Public Health

x Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

03/08/2022

204

Contract Award

 

Location:

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$169,326.08

$169,326.08

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$169,326.08

$169,326.08

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$169,326.08

$169,326.08

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: May 07, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B