Legislation Details

File #: 24-4223    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 7/3/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval to execute an amendment with GC Engineering Inc. in the amount of $303,332.42 for professional engineering services to provide improvements to Telge Rd Segment 5 - from 1,780-ft North of Telge Ranch Rd to 300-ft North of Grant Rd - 2014, UPIN 23103MF2QF01, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 23103MF2QF01

Vendor/Entity Legal Name (if applicable): GC Engineering Inc.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval to execute an amendment with GC Engineering Inc. in the amount of $303,332.42 for professional engineering services to provide improvements to Telge Rd Segment 5 - from 1,780-ft North of Telge Ranch Rd to 300-ft North of Grant Rd - 2014, UPIN 23103MF2QF01, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

Background and Discussion:

 

This amendment includes a variety of changes to the study and the design including adjustments to the alignment as well as additional detention pond survey, map preparation, design, geotechnical, and environmental work that will be required.

 

Expected Impact:

 

This amendment will allow the project alignment as well as the detention pond to be optimized to better fit the conditions. The amendment will also allow all the acquisition maps to be prepared as well as an updated topo survey to fit the recently changed site conditions. 

 

Alternative Options:

 

An alternative would be to not optimize the alignment or conduct the work to allow the topo surveying and the acquisition maps survey to be conducted and not completing the design and construction of the project.

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

07/19/2022

83

Authorization to Negotiate

11/15/2022

46

Professional Service Agreement

1/10/2023

30

Amendment #1

 

Location: Telge Road

 

Address (if applicable): Telge Road

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$303,332.42

$303,332.42

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$303,332.42

$303,332.42

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$303,332.42

$303,332.42

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: July 15, 2024

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): Agreement