Legislation Details

File #: 25-6169    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/30/2025 In control: Commissioners Court
On agenda: 10/16/2025 Final action: 10/16/2025
Title: Request for approval of a change in contract with Spawglass Construction Corp., in connection with 7400 W Sam Houston Pkwy (Art Storey Park) - New Pavilion - 2022, adding 45 calendar days, with an addition in the amount of $74,293.93. Job No. 24/0202-1, UPIN 23104MF2MF01, Precinct 4, MWBE Contracted Goal: 25.75%, MWBE Current Participation: 25.52%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

 

Secondary Department: Commissioner, Precinct 4

Secondary Department Head/Elected Official: Commissioner Briones

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0202, UPIN 23104MF2MF01

Vendor/Entity Legal Name (if applicable): Spawglass Construction Corp.

 

MWBE Contracted Goal (if applicable): 25.75%

MWBE Current Participation (if applicable): 25.52%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Spawglass Construction Corp., in connection with 7400 W Sam Houston Pkwy (Art Storey Park) - New Pavilion - 2022, adding 45 calendar days, with an addition in the amount of $74,293.93. Job No. 24/0202-1, UPIN 23104MF2MF01, Precinct 4, MWBE Contracted Goal: 25.75%, MWBE Current Participation: 25.52%.

end

 

Background and Discussion:

Project includes the construction of a new 658 sf hexagonal concrete pavilion at Art Storey Park located at 7400 West Sam Houston Parkway in Precinct 4. The concrete pavilion has a custom wooden roof structure with glazed clay tiles that were pre-purchased and imported from Taiwan for installation by the awarded contractor.

 

The change in contract includes the costs associated with providing the necessary materials, equipment, and labor for additional work involving the installation of the pre-purchased roof structure and tiles. Services include repairing cracks in the wooden roof members, filling of cracks on wood surfaces and sanding smooth prior to painting, for the installation of roof waterproofing, for the application of mortar to roof structure necessary to properly attach clay tiles and seal roof end cap openings, for the application of clear acrylic coating after finish painting is applied, and for additional material essential to complete the roof system, clay tiles, and various glazed ornaments mounted on the roof.

 

 

Expected Impact:

Upon completion, the project will provide park visitors with a durable and distinctive covered structure. Approval of this change order will ensure that all necessary measures are taken to properly install and complete the pre-purchased roof system.

 

Alternative Options:

Commissioners court could postpone the change order, which will delay project completion and create significant negative impacts on work already completed due to continuous exposure to the elements.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: I: Increase access to safe, clean, and enjoyable green space.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  I2: Formally adopt Imagination Zones as a preferred development approach within the County that improves connectivity to green space.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/29/2023

23-4942

Approval to Advertise

06/25/2024

24-3927

Approval to Advertise

03/26/2024

24-1817

Approval to Reject Bids

06/25/2024

24-3927

Approval to Advertise

02/06/2025

25-1062

Contract Award

02/27/2025

25-1222

Correction to vendor name

 

Location:

Address (if applicable): 7400 West Sam Houston Parkway South, Houston, TX 77072

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper - 3239

$

$74,293.93

$74,293.93

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$74,293.93

$74,293.93

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$74,293.93

$74,293.93

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 10/16/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Dr. Ronald Lerner, DBA, MScE, LSSBB, IAEng - Director, Facilities Design & Construction, Office of the County Engineer

 

Attachments (if applicable): Change Order