File #: 25-0621    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/12/2025 In control: Commissioners Court
On agenda: 1/23/2025 Final action: 1/23/2025
Title: Request for approval of a change in contract with Icon GC, LLC, in connection with final construction of Forest Shadows Subdivision Drainage Improvements 2018, adding 32 calendar days, with an addition in the amount of $77,028.15, Job No. 23/0061-2, UPIN 19104MF13X01, Precinct 3, MWBE Contracted Goal: 30%, MWBE Current Participation: 28.81%.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job. No. 23/0061, UPIN 19104MF13X01

Vendor/Entity Legal Name (if applicable): Icon GC, LLC

 

MWBE Contracted Goal (if applicable): 30%

MWBE Current Participation (if applicable): 28.81%

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Icon GC, LLC, in connection with final construction of Forest Shadows Subdivision Drainage Improvements 2018, adding 32 calendar days, with an addition in the amount of $77,028.15, Job No. 23/0061-2, UPIN 19104MF13X01, Precinct 3, MWBE Contracted Goal: 30%, MWBE Current Participation: 28.81%.

end

 

Background and Discussion:

The Forest Shadows Subdivision is located in North Harris County, north of FM 1960, east of Rayford Road, and southwest of Cypress Creek. The subdivision is within the Cypress Creek Watershed. The Forest Shadows subdivision is currently drained by roadside ditches and culverts. A portion of the drainage is directed to Theiss Road at the intersection of Forest Glade Drive and eventually through the adjacent subdivision. The southeast portion drains to Turkey Creek. The scope of work for this project consists of regrading roadside ditches, replacing culverts and driveways, construction of a detention basin for mitigation, and roadway improvements consisting of extending Broadmark Lane to provide access to the detention pond and the reconstruction of segments of Theiss Road, Forest Glade Drive and Broadmark Lane.

 

The change in contract includes the following:

 

Quantity Adjustment: The below line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

 

•                     The increase of quantities on overrun line item numbers 9, 16, 18, and 20 for an addition in the amount of $37,815.02.

•                     The decrease of quantities on underrun line item numbers 1, 5, 7, 8, 10, 11, 13, 15, 17, 19, 21, 22, 23, 24, 25, 26, 27, 28, 30, 32, 34, 35, 37, 38, 39, 43, 44, 45, 46, 47, 48, 49, 50, 52, 55, 56, 57, 58, 59, 60, 62, 64, 65, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77 and 78 for a deduction in the amount of $305,075.18.

 

New Line Items: Adding new line items on the project for completion of the proposed scope of work.

 

•                     Added new line item numbers 80 and 81 for Erosion Blankets and SET replacement with runners for an addition in the amount of $49,055.71.

•                     Added new line item number 82 - cost impacts due to design revisions involving outfall modification at channel, modifications extending from channel to roadside ditch, SET at roadside ditch leading to detention basin, and changes to the proposed scope of work throughout constructing the project for an addition in the amount of $295,232.66.

•                     Added 32 calendar days to the project time for changes to the proposed scope of work throughout constructing the project.

 

The above additions and deductions result in a net change in the amount of $77,028.15 and 32 calendar days.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Forest Shadows subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A                     

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

03/14/2023

369 (23-1892)

Transmittal - Advertisement

04/04/2023

231 (23-1892)

Award of Construction Contract- iCON GC, LLC.

06/04/2024

66 (24-3355)

Contract Amendment - (23/0061-1) for additional funds and extension of project term

 

Location: Forest Shadows Drainage Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

$77,028.15

$77,028.15

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$77,028.15

$77,028.15

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$77,028.15

$77,028.15

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/23/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC)