Harris County Logo
File #: 24-5651    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 9/5/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval to execute an interlocal agreement with Northwest Harris County Municipal Utility District No. 23 to construct and maintain a trail and sidewalks for the Sablechase Neighborhood, located around the detention pond at Sablechase Drive & TC Jester Blvd, UPIN 21101MF1YU01, Precinct 1.
Attachments: 1. 24-5651-22GEN3411_Joint Participation_Northwest HC MUD No. 23_Partially Executed

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

 

Project ID (if applicable): UPIN 21101MF1YU01

Vendor/Entity Legal Name (if applicable): Northwest Harris County Municipal Utility District No. 23

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable):N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to execute an interlocal agreement with Northwest Harris County Municipal Utility District No. 23 to construct and maintain a trail and sidewalks for the Sablechase Neighborhood, located around the detention pond at Sablechase Drive & TC Jester Blvd, UPIN 21101MF1YU01, Precinct 1.

end

 

Background and Discussion:

The scope of work for this project consists of the installation of approximately 2,200 LF of concrete trail around HCFCD Detention Basin P545-07-01 and approximately 1,100 LF of connecting concrete trail / sidewalk. The trail / sidewalk width varies from 5-to-8 ft. The project will also expand the existing swale system around the detention basin in order to mitigate floodplain fill and provide appropriate drainage paths.

This agreement will allow Northwest Harris County Municipal Utility District No. 23 to maintain the pond after construction.

 

 

Expected Impact:

Providing the trail and sidewalk will ensure reliable and safe pedestrian transportation and efficient movement of people for nearby communities and residents.

 

 

Alternative Options:

Court may elect to not move forward, and Harris County can explore additional options, however this will cause project delays.

 

Alignment with Goal(s):

X Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): Around the detention pond at Sablechase Drive & TC Jester Blvd.

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: September 19, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Cassandra Green, P.E., Director of Technical Services, Harris County Engineering Department

 

Attachments (if applicable): Interlocal Agreement