Legislation Details

File #: 26-6389    Version: 1 Name:
Type: Investment Memo Status: Agenda Ready
File created: 9/11/2026 In control: Commissioners Court
On agenda: 9/22/2026 Final action:
Title: Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations projects, for an incremental amount of $2,581,000 for a total authorization of $3,600,000 for FY 2027.  
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Managing Department: County Engineer

Managing Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Fire, Life Safety, and Electrical System Repair and Renovations

Project ID (if applicable): MF0DU

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $2,581,000

Total Estimated Project Cost: $17,470,000 (FY27-31)

Request Summary:

title

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations projects, for an incremental amount of $2,581,000 for a total authorization of $3,600,000 for FY 2027

end

 

Project Description:

These funds are intended to support new construction and renovations in the coming fiscal year and the continuous lifecycle management project to identify and address all required upgrades and enhancements of fire, safety, and electrical systems in County facilities that are currently maintained by Office of the County Engineer. This includes fire safety systems, controls, and electrical service upgrades.

 

Below are the planned allocations; there might be changes in the County’s needs that result in minor operational changes and funding for the projects throughout the Fiscal Year. The County Engineer is Authorized to adjust scope and projects at their discretion within the program. Any additional financial authorizations would go through Commissioners Court approval.

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

911 Call Center - Shutter Replacements (Batch 2)

$450K

FY2027

Annex 60 - Upgraded Safety Systems and Fencing

$706K

FY2027

Central Plant - Remote Racking for Switch Gear

$898K

FY2027

Evelyn Meador Branch Library - High Speed Rollup Doors

$340K

FY2027

PETS Vet Clinic - Access Ladders and Related Safety Landing and Railings

$157K

FY2027

Shelia Jackson Lee Admin Building - Power, IT/Data, Exhaust and Fire System Upgrades

$540K

FY2027

FY 2027 Authorization

$3,091K

 

Contingency

$509K

 

FY 2027 Total Authorization

$3,600K

 

Unencumbered Carryforward from FY2026

$(1,019)K

 

FY 2027 Incremental Authorization

$2,581K

 

 

Justification & Alternatives:

The county has multiple projects planned across the county, including replacements or upgrades to existing facilities. Failure to maintain, modernize, and upgrade the County's existing facilities will result in more expensive maintenance, as well as the closure of certain areas or facilities for non-code compliance and, most importantly, risks to life/safety. Fire safety systems and electrical upgrades are critical and required to support the building infrastructure and to allow occupancy. Fire safety and electrical issues involve building code and safety requirements.

 

The Office of the County Engineer (OCE) continues to experience the effects of previous years’ inflation regarding materials and labor for construction projects. The cost of individual materials varied significantly the previous fiscal year due to national and international events; this is expected to continue through the next Fiscal Year.

 

Not funding this program would lead to increased maintenance and repair costs and, in some cases, could create hazards to life and safety.  Delays in project timeline may increase costs due to increased deterioration of infrastructure, potential bid increases, and increases in material and labor costs.

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): S3: Increase accessibility and reliability of County cooling and warming centers.

Housing Initiative (Goal 6): N/A

 

Previous Court Action:

Date

Agenda Item #

Action Taken

9/11/2018

1.v.2

$1.5M authorization

10/9/2018

4.c

$1.5M CP allocation

6/4/2018

 

CIP $1M authorization in interim CIP

8/27/2019

4.e.4

$1M CP allocation

1/7/2020

II.1.d

$5M authorization in FY20 CIP

7/14/2020

4.h.7

$2M CP allocation

3/9/2021

88

Harris County - Proposed Capital Improvements Program; Facility and Maintenance Projects: Fire, Life Safety, and Electrical System Repair and Renovations Countywide, pages 281 and 288 ($7,894,150 authorization for FY21-22)

5/25/2021

94

$4M CP allocation

8/24/2021

94

$5,186,611 incremental authorization reduction; CP reduction of $725K

3/8/2022

108

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an additional $7,107,000 for a SFY 22 authorization of $7,710,000 for Facilities and Property Maintenance and request for approval of commercial paper funding for Engineering for the project in the additional amount of $4,800,000 for a total of $12,575,000. (p.13)

10/18/2022

123

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an additional $4,395,000 for a FY 2023 authorization of $11,451,000. 22-6657

8/29/2023

23.15

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an additional $5,363,000 for a FY24 authorization of $7,611,000.

6/4/2024

24.16

Request for approval of commercial paper funding for the Office of the County Engineer for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project in the additional amount of $1,000,000 for a total CP funding of $13,575,000.

11/12/2024

111/ 24-7284

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an incremental authorization of $9,464,000 for a total FY25 authorization of $9,864,000 and request for commercial paper funding for an amount of $1,000,000

1/09/2025

 18

Request for approval of commercial paper funding for the Office of the County Engineer for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project in the additional amount of $6,170,000 for a total CP funding of $20,745,000.

 

Address: Countywide

Precinct(s): Countywide

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 9/22/2026

Anticipated Implementation Date (if different from Court date): 10/1/2026

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, First Assistant County Attorney-Legal Operations, 8/15/2024

Department Approval by:

Ross Hosket, P.E., CFM, ENV-SP, Director - Building Operations Services

Samuel Peña, Chief Operating Officer, Office of County Engineer

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 9/11/2026

________________________________________

Commercial Paper Request (For OMB use only):

Receiving Department: N/A

Project PeopleSoft ID: N/A

CP Series Description: N/A

OMB Financial Management Contact: N/A