Legislation Details

File #: 25-5131    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/13/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Request for approval of a change in contract with Yellowstone Landscape Central, Inc in connection with final construction for On-Call - Maintenance Mowing Humble Camp Area, Precinct 3 - 2022, with an addition in the amount of $82,992.40, Job No. 22/0065-2, UPIN 22103MF2HJ01, Precinct 3, MWBE Contracted Goal: 19.67%, MWBE Current Participation: 19.73%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0065, UPIN 22103MF2HJ01 

Vendor/Entity Legal Name (if applicable): Yellowstone Landscape Central, Inc.

 

MWBE Contracted Goal (if applicable): 19.67%

MWBE Current Participation (if applicable): 19.73%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Yellowstone Landscape Central, Inc in connection with final construction for On-Call - Maintenance Mowing Humble Camp Area, Precinct 3 - 2022, with an addition in the amount of $82,992.40, Job No. 22/0065-2, UPIN 22103MF2HJ01, Precinct 3, MWBE Contracted Goal: 19.67%, MWBE Current Participation: 19.73%.

end

 

Background and Discussion:

Project includes mowing services at various locations throughout the Humble Camp for Precinct 3.  The terms of services in connection with purchase order is being closed at the request of the Precinct.  Change allows the Contractor to be compensated for the additional roads mowed that were added at the request of Precinct 3. The change includes adding $82,992.40 to the contract.

 

Expected Impact:

Change allows Contractor to be compensated for work completed on the project.

 

Alternative Options:

Maintain the original scope of the project.

 

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F2: Improve data collection, utilization, and availability to drive better transportation safety decision-making.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/23/2024

295 (24-2355)

Contract Renewal

09/19/2024

50 (24-5706)

Contract Amendment #1 for additional funds

 

Location:

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$82,992.40

$82,992.40

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$82,992.40

$82,992.40

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$82,992.40

$82,992.40

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/26/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B