Legislation Details

File #: 24-6572    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/14/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Request for approval of a change in contract with Amtech Elevator Services in connection with 1111 Fannin - Elevator Modernization - 2024, with an addition in the amount of $218,000.00, UPIN 24035MF3BW01, Precinct 1, MWDBE Contracted Goal: 3%, MWDBE Current Participation: 0%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 24035MF3BW01 Job ID: 230164

Vendor/Entity Legal Name (if applicable): Amtech Elevator Services

MWDBE Contracted Goal (if applicable): 3%

MWDBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Amtech Elevator Services in connection with 1111 Fannin - Elevator Modernization - 2024, with an addition in the amount of $218,000.00, UPIN 24035MF3BW01, Precinct 1, MWDBE Contracted Goal: 3%, MWDBE Current Participation: 0%.

end

 

Background and Discussion:

Change Order includes additional costs to accelerate the schedule for the 2 shuttle elevators and 2 garage elevators.

 

Expected Impact:

Without the renovations of the interior of the elevators, the modernization efforts would be incomplete. The elevators would not have the correct lighting, notifications, buttons, and handicap requirements for a complete project. The motor must be placed as the elevators would be un-operatable for a building with over 1,000 Harris County employees.

 

Alternative Options:

If the timeline is not expedited, then Harris County employees would incur additional work hardship that could have otherwise been prevented.

 

Alignment with Goal(s):

x Justice and Safety

_ Economic Opportunity

_ Housing                     

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/29/2023

321

Contract Award for Elevator Repair, File # 23-4943

10/08/2024

66

Change Order #1

 

Location:

Address (if applicable): 1111 Fannin St.

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$218,000.00

$218,000.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$218,000.00

$218.000.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$218.000.00

$218.000.00

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: October 29, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Truitt Rounsavall, Director Capital Projects Facilities - MEP, Harris County Engineering Department

 

Attachments (if applicable): Included Change Order