Legislation Details

File #: 26-7667    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 11/6/2026 In control: Commissioners Court
On agenda: 11/19/2026 Final action:
Title: Request for approval of a change in contract with Precise Services, Inc., in connection with South Belt Basin Improvement, with an addition in the amount of $21,894.36, Job No. 26/0049-1, UPIN 24102MF34B01, Precinct 2, MWBE Contracted Goal: 26.11%, MWBE Current Participation: 100%.
Attachments: 1. 26-7667-CIC-24102MF34B01-South Belt Basin-26-0049-1-Precise Svcs-P2-11192026.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 26/0049, UPIN 24102MF34B01

Vendor/Entity Legal Name (if applicable): Precise Services, Inc.

 

MWBE Contracted Goal (if applicable): 26.11%

MWBE Current Participation (if applicable): 100%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Precise Services, Inc., in connection with South Belt Basin Improvement, with an addition in the amount of $21,894.36, Job No. 26/0049-1, UPIN 24102MF34B01, Precinct 2, MWBE Contracted Goal: 26.11%, MWBE Current Participation: 100%.

end

 

Background and Discussion:

This project is part of the Precinct 2 Commissioner Adrian Garcia's Revive2Thrive initiative to focus on revitalization rather than gentrification by empowering communities and creating opportunities for our existing neighborhoods to be more resilient, inclusive, and thriving.  The project consists of a 10' wide walking trail, concrete parking lot, parking spaces, park benches, lighting, and trash cans around the South Belt Stormwater Detention Basin.

This change order is tied to PCO -1: The proposed Change Order in the amount of $21,894.36 is necessary to incorporate additional field work identified during construction that was not included in the original contract bid items.  The additional work consists of 187 LF of 2-inch Schedule 80 PVC Conduit, three Type D Harris County pull boxes, and the removal and disposal of 191 LF of existing fence, which are required to complete the project in accordance with field conditions and project requirements.

This $21,894.36 Change Order represents approximately 1.86% of the original contract amount, with no additional days to the contract time.

Expected Impact: The changes enable adding new item quantities to the contract, ensuring the project aligns with its originally intended objectives.  This change order adds $21,894.36 to the project contract amount, with no additional days.

Alternative Options: No alternative options: If no action is taken, the basin improvement will not be completed.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/16/2026

263 (26-2281)

Contract Award

 

Location:

Address (if applicable): 11770 South Fork Boulevard at Beamer Road

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other  3021

$

$21,894.36

$21,894.36

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$21,894.36

$21,894.36

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$21,894.36

$21,894.36

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 11/19/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B