Legislation Details

File #: 24-7284    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 11/4/2024 In control: Commissioners Court
On agenda: 11/12/2024 Final action: 11/12/2024
Title: Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an incremental authorization of $9,464,000 for a total FY25 authorization of $9,864,000 and request for commercial paper funding for an amount of $1,000,000.
Sponsors: Mony Hossain

Department: County Engineer

Department Head: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Fire, Life Safety, and Electrical System Repair and Renovations Countywide

Project ID (if applicable): MF0DU

Vendor Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Managing Entity: County Engineer

Incremental Authorization Requested: $9,464,000

Total Estimated Project Cost: $49,320,000 (FY25-29)

 

Request Summary:

 

title

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an incremental authorization of $9,464,000 for a total FY25 authorization of $9,864,000 and request for commercial paper funding for an amount of $1,000,000.

end

 

Project Description:

These funds are intended to support new construction in the coming fiscal year and the continuous lifecycle management project to identify and address all required upgrades and enhancements of fire, safety, and electrical systems in County facilities that are currently maintained by Harris County Engineering. This includes fire safety systems, controls, and electrical service upgrades.

 

Project Scope:

Impending new construction and existing county facilities require upgrades or replacement to the fire safety and electrical systems. Harris County Engineering will be incorporating or updating fire safety systems across the county to comply with state and federal code requirements. The detailed project scope for FY25 is listed in the table below.

There might be changes in the County’s needs that result in minor operational changes for the project throughout the Fiscal Year, but the overall scope will remain the same, and any additional authorization would go through Commissioners Court approval.

Justification:

The county has multiple projects planned across the county and replacement or upgrades to existing facilities. Failure to continue implementing the required upgrades or replacements to the County's existing facilities will result in more expensive maintenance, as well as the closure of certain areas or facilities for non-code compliance and, most importantly, risks to life/safety. Fire safety systems and electrical upgrades are critical and or required to support the building infrastructure and to allow occupancy. Fire safety and electrical issues involve building code and safety requirements.

 

HCED continues to experience the effects of previous years’ inflation regarding materials and labor for construction projects. Although inflation for costs of materials and labor increased at the historical average in FY2025, the increase from previous years is expected to remain.

 

Alternatives and Engagement:

Not funding this program would lead to an increased maintenance and repair costs, and, in some cases, could create hazards to life and safety.  Delay in project timeline may increase costs due to increased deterioration of infrastructure, potential bid increases, and increase in material and labor costs.

Anticipated Project Expenditures and Timeline:

Scope of Work

 FY25 Forecast Estimate

Estimated Completion

1010 Lamar - Stairwell Pressurization - 2024

$1,000K

FY 2025

1001 Preston - 9th Floor Precinct 4 Office Renovation - 2024

$50K

FY 2025

1201 Franklin (Annex 65) - Smoke Evacuation System including Fan Towers

$500K

FY 2026

HCED Maintained Buildings - Fire Systems & Replacement, and Enhancements.

$3,450K

FY 2025

HCED Maintained Buildings - Fire Monitoring Systems, Enhancements, and New Installs.

$60K

FY 2025

14350 Wallisville Rd (Annex 26) - MEP Upgrades - 2023 (fire-safety)

$85K

FY 2025  

14350 Wallisville Rd (Annex 26) - MEP Upgrades - 2023 (electrical)

$175K

FY 2025  

406 Caroline (Annex 18) - General Electrical Improvements - 2023 - (Elect)

$150K

FY 2025

HCSO/HCFMO Campus - Electrical Upgrades - 2023

$250K

FY 2025  

HCED Maintained Buildings - General Electrical and UPS Projects

$2,500K

FY 2025 

Contingency on Projects

$1,644K

 

Total FY2025 projects

$9,864K

 

Unencumbered current balance

$(400)K

 

Total

$9,464K

 

Note: Certain work packages will be completed after the end of FY25 but purchase orders will need to be encumbered in FY25 to ensure on-time delivery & installation, and thus are included in the total incremental ask.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Previous Court Action:

Date

Agenda Item #

Action Taken

9/11/2018

1.v.2

$1.5M authorization

10/9/2018

4.c

$1.5M CP allocation

6/4/2018

 

CIP $1M authorization in interim CIP

8/27/2019

4.e.4

$1M CP allocation

1/7/2020

II.1.d

$5M authorization in FY20 CIP

7/14/2020

4.h.7

$2M CP allocation

3/9/2021

88

Harris County - Proposed Capital Improvements Program; Facility and Maintenance Projects: Fire, Life Safety, and Electrical System Repair and Renovations Countywide, pages 281 and 288 ($7,894,150 authorization for FY21-22)

5/25/2021

94

$4M CP allocation

8/24/2021

94

$5,186,611 incremental authorization reduction; CP reduction of $725K

3/8/2022

108

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an additional $7,107,000 for a SFY 22 authorization of $7,710,000 for Facilities and Property Maintenance and request for approval of commercial paper funding for Engineering for the project in the additional amount of $4,800,000 for a total of $12,575,000. (p.13)

10/18/2022

123

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an additional $4,395,000 for a FY 2023 authorization of $11,451,000. 22-6657

8/29/2023

23.15

Request for approval of a Final Investment Memo for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project for an additional $5,363,000 for a FY24 authorization of $7,611,000.

6/4/2024

24.16

Request for approval of commercial paper funding for the Office of the County Engineer for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project in the additional amount of $1,000,000 for a total CP funding of $13,575,000.

 

Address: Countywide

Precinct(s): Countywide                     

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$1,000.000

$1,000,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$1,000,000

$1,000,000

$

Total Funding Request

$

$1,000,000

$1,000,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

 

Anticipated Court Date: 11/12/2024

Anticipated Implementation Date (if different from Court date):

Legal funding compliance confirmed by: Paige Abernathy, Assistant County Attorney, 8/15/2024

Department Approval by: Rosalie Brockman, Director, Resiliency and Sustainability Operations Services

OMB CIP Team Approval by: Wanwei Tang, Analyst - Capital Projects and Infrastructure, 7/3/24

 

Commercial Paper Request (For OMB use only):

Receiving Department: County Engineer

Project PeopleSoft ID: MF0DU

CP Series Description: Commercial Paper Series D can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

 

Commercial Paper is being requested for the Fire, Life Safety, and Electrical System Repair and Renovations Countywide project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.

OMB Financial Management contact: Amy Perez, Deputy Executive Director, Office of Management and Budget