Legislation Details

File #: 24-2611    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 4/22/2024 In control: Commissioners Court
On agenda: 5/7/2024 Final action: 5/7/2024
Title: Request for approval of a change in contract with Durwood Greene Construction, Co., in connection with Clay Road 2 - West of Porter Road to West of Ventana Prairie Drive, adding 236 calendar days, with an addition in the amount of $445,403.69, Job No. 21/0155-2, UPIN 171033954822, Precinct 4, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0155, UPIN 171033954822

Vendor/Entity Legal Name (if applicable): Durwood Greene Construction, Co.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Durwood Greene Construction, Co., in connection with Clay Road 2 - West of Porter Road to West of Ventana Prairie Drive, adding 236 calendar days, with an addition in the amount of $445,403.69, Job No. 21/0155-2, UPIN 171033954822, Precinct 4, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program.

end

 

Background and Discussion:

Project includes construction of underground utilities and 4 lane asphalt pavements on Clay Road and 4 lane concrete pavements on Porter Road plus a new signal at the intersection.

 

Change Includes

•                     Additional Detour quantities for Porter Road

•                     Stabilized construction access payment

•                     Additional temporary Commercial Driveways

•                     Additional work surrounding Ventana Ridge Drive that was not shown on the original plans

•                     Concrete collars for RCB and RCP due to utility conflicts

•                     Added quantity to pay for overruns of existing bid items

 

Expected Impact:

Changes allow for compensation for the additional work performed and adequate time to perform these additional tasks.

 

Alternative Options:

Eliminate the additional work in the areas and not complete the project.

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

07/20/2021

314

Contract Award

04/25/2023

41

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable): Clay Road

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other Fund 3109

$

$445,403.69

$445,403.69

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$445,403.69

$445,403.69

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$445,403.69

$445,403.69

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: May 07, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B