Legislation Details

File #: 24-6045    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/20/2024 In control: Commissioners Court
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Request for approval of a change in contract with SER Construction Partners LLC, in connection with final construction of Aldine Mail Route Rd from Slater Lane to Aldine Westfield Road, adding 107 calendar days, with a deduction in the amount of $980,918.88, Job No. 22/0292-3, UPIN 18102MF0SQ01, Precinct 2, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 32.54%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0292, UPIN 18102MF0SQ01

Vendor/Entity Legal Name (if applicable): SER Construction Partners LLC

 

MWDBE Contracted Goal (if applicable): 26%

MWDBE Current Participation (if applicable): 32.54%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with SER Construction Partners LLC, in connection with final construction of Aldine Mail Route Rd from Slater Lane to Aldine Westfield Road, adding 107 calendar days, with a deduction in the amount of $980,918.88, Job No. 22/0292-3, UPIN 18102MF0SQ01, Precinct 2, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 32.54%.

end

 

Background and Discussion:

The project includes the reconstruction of Aldine Mail Route Road from Slater Lane to Aldine Westfield Road including concrete pavement replacement and storm sewer construction.  This change in contract also includes the final reconciliation of actual quantities used in construction against the bid quantities as follows:

 

PCO-27 - Center Point Electric had a High Voltage Electrical Duct bank in conflict with three lateral storm sewer connections required to complete the storm sewer system from station 110+49 to 118+20 South side of AMR, which delayed the contractor 28 days to his critical path work in completing the storm sewer and placing the concrete pavement.  The plans indicated that the electric duct bank was located deeper than it was.  As a result, CNP Electric had to hire their own subcontractor to demolish the top half of the duct bank, while the bottom half remained live with high-voltage electricity. $0.00 - 28 Days.

 

PCO-34 - As per TCP Phase 3, it is required to remove and replace the median sections back to original conditions near station 110+00.  However, there are no pay items associated with the 104 SY of subgrade and brick pavers re-installation.  $18,451.37 - 4 Days.

 

PCO-35 - We need to change an existing 24" grate top inlet to a manhole top in order to pour the sidewalk. $1,189.31 - 0 Days.

 

PCO-36 - Harris County will need to relocate two (2) electrical service risers on Harris County Right-of-Way in conflict with proposed construction. Coordination delays between the Electrician Sub and Center Point Electric delayed the relocation work by 72 days. $75,558.91 - 72 Days.

 

PCO-37 - Three new Curb Inlet Drains are needed to drain adjacent properties that are lower than the sidewalks causing flooding. $15,099.81 - 3 Days.

 

PCO-38 - Per the Special Requirements of the Specification, Contractor is entitled for price adjustment due to industry wide changes.  The total volume of concrete has been used for the project from April 2023 to the end of the project is approximately 8,644 CY and price went up by $6/CY.  The total Price will be equal to $52,382.64 with 1% bond included. $52,382.64 - 0 Days.

 

PCO-39 through PCO-46 - FINAL ADJUSTMENTS - OVERRUNS AND DEDUCTS - $-1,143,600.92 - 0 Days.

 

Expected Impact:

This action allows for unused funds to be returned to Harris County.

 

Alternative Options:

Action required to return unused funds.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/27/2022

22-5704

Contract Award

07/18/2023

23-4017

Contract Amendment #1 for additional funds and extension of project term

10/31/2023

23-6243

Contract Amendment #2 for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3002, 1070, 3021

$

-$980,918.88

-$980,918.88

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

-$980,918.88

-$980,918.88

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Other

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

-$980,918.88

-$980,918.88

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date:  October 08, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department