Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): Job No. 23/0020; UPIN: 20090MF1H001
Vendor/Entity Legal Name (if applicable): Precise Services, Inc.
MWDBE Contracted Goal (if applicable): 21%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Precise Services, Inc., in connection with Westfield Pines and Village Subdivisions Drainage Improvements - 2019, Job No. 23/0020, UPIN 20090MF1H001, Precinct 4, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 100%.
end
Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.
Expected Impact:
N/A
Alternative Options:
N/A
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
03/14/2023 |
23-1530 |
Contract Award - Precise Servicies, Inc. |
|
09/19/2023 |
23-5375 |
Contract Amendment |
Location: Westfield Pines and Village Subdivisions Drainage Improvements - 2019
Address (if applicable): N/A
Precinct(s): Precinct 4
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Cour Date: October 8, 2024.
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): Substantial Completion Certificate