Skip to main content
Harris County Logo
File #: 25-2636    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 4/23/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action: 5/8/2025
Title: Request for approval of an agreement with Agha Engineering, LLC, in the amount of $1,061,533.65, to provide preliminary engineering services in support of channel conveyance improvements and a stormwater detention basin on HCFCD Unit H125-00-00 (Hunting Bayou Watershed, Bond ID F-17, Project ID H125-00-00-E001, Agreement No. 2024-32, Precincts 1 and 2, MWBE Contracted Goal: 19.6%).
Attachments: 1. 041025 AGMT AGHA 2024-32 PCT 1 AND 2 backup.pdf

Primary Department: Flood Control District

Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): H125-00-00-E001

Vendor/Entity Legal Name (if applicable): Agha Engineering, LLC

 

MWBE Contracted Goal (if applicable): 19.6%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an agreement with Agha Engineering, LLC, in the amount of $1,061,533.65, to provide preliminary engineering services in support of channel conveyance improvements and a stormwater detention basin on HCFCD Unit H125-00-00 (Hunting Bayou Watershed, Bond ID F-17, Project ID H125-00-00-E001, Agreement No. 2024-32, Precincts 1 and 2, MWBE Contracted Goal: 19.6%).

end

 

Background and Discussion:

This agreement will provide preliminary engineering report for the support of Right-of-Way Acquisition, Design and Construction of Wallisville Outfall. The preliminary engineering report will include hydraulic analysis for three alternatives for stormwater detention basin and channel improvements, and to evaluate the costs and benefits of each alternative, and to make recommendation of most feasible alternative. The project area is located at the Hunting Bayou Watershed along the channel H125-00-00, just north of the intersection of I-10E and I-610. This project is funded by the 2018 bond program, charter ID F-17. This project occurs in the 3rd quartile under the 2022 Prioritization Framework approved by Commissioners Court.

 

Expected Impact:

The project seeks to reduce flood risks and strengthen resiliency in the Hunting Bayou watershed by deepening of the existing channel, increasing culvert capacity and proposed a detention basin to mitigate increased flooding in the Gellhorn Drive area.

 

This agreement is to prepare a preliminary engineering report in support of Right-of-Way Acquisition, Design and Construction of Wallisville Outfall Project.

 

Alternative Options:

The alternative to approving this item would be not to continue PER, design and construction, which would result in flood risk will remain the same.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H2: Evaluate the feasibility and potential impacts of substantial, large-scale flood mitigation measures to provide equitable and transformational regional benefits.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/25/2024

184.

ATN

 

Location: H125-00-00

Address (if applicable): Intersection of the Gellhorn Drive and H125-00-00 Channel

Precinct(s): Precincts 1 & 2

 

Fiscal and Personnel Summary

Service Name

4.a.3 - Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$1,061,533.65

$1,061,533.65

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$1,061,533.65

$1,061,533.65

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$1,061,533.65

$1,061,533.65

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/8/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Agreement and Map