File #: 25-0072    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/22/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval of a change in contract with Builders United, LLC., in connection with final construction of Dennis Johnston Park, Cabin 2 - 2019, with an addition in the amount of $650.00, Job No. 22/0337-2, UPIN 20104MF1E901, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation Goal: 25.15%.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0337, UPIN  20104MF1E901

Vendor/Entity Legal Name (if applicable): Builders United, LLC

 

MWBE Contracted Goal (if applicable): 26%

MWBE Current Participation (if applicable): 25.15%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Builders United, LLC., in connection with final construction of Dennis Johnston Park, Cabin 2 - 2019, with an addition in the amount of $650.00, Job No. 22/0337-2, UPIN 20104MF1E901, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation Goal: 25.15%.

end

 

Background and Discussion:

Project includes reconstruction of Cabin 2 at Dennis Johnston Park for Harris County Precinct 3.


This change in contracts includes the final adjustment (reconciliation of actual quantities used in construction against the bid quantities). ($650.00).

 

Expected Impact:

Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated.

 

Alternative Options:

Maintain the original scope of the project.

 

 

 

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/29/2022

22-7539

Contract Award

08/08/2023

23-4439

Contract Amendment #1 for additional funds

 

Location:

Address (if applicable): Dennis Johnston Park

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1000 - General Fund

$

$650.00

$650.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$650.00

$650.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$650.00

$650.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/9/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Engineering Department

 

Attachments (if applicable): County Auditor’s Form 1258B.