File #: 24-3053    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/16/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a change in contract with WadeCon, LLC in connection with Telge Road 2 - Moray View Drive to Wyman Gordon Driveway - 2019, with an addition in the amount of $40,030.75, Job No. 21/0431-2, UPIN 201033962813, Precinct 3, MWDBE Contracted Goal: 15%, MWDBE Current Participation: 15.90%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0431, UPIN 201033962813

Vendor/Entity Legal Name (if applicable): WadeCon, LLC

 

MWDBE Contracted Goal (if applicable): 15%

MWDBE Current Participation (if applicable): 15.90%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with WadeCon, LLC in connection with Telge Road 2 - Moray View Drive to Wyman Gordon Driveway - 2019, with an addition in the amount of $40,030.75, Job No. 21/0431-2, UPIN 201033962813, Precinct 3, MWDBE Contracted Goal: 15%, MWDBE Current Participation: 15.90%.

end

 

Background and Discussion:

This project consists of removal and replacement of the existing roadway pavement along Telge Road, from

Moray View Drive to Wyman Gordon Driveway located in Harris County Precinct 3.

 

This change in contracts includes Cost of overrun and underrun of bid items based on the actual quantities of materials furnished and installed on the jobsite. ($40,030.75 - 0 days).

 

Expected Impact:

Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated.

 

Alternative Options:

Maintain the original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

02/22/2022 

234

Contract Award

04/04/2023

50

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable): Telge Road

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other Fund 3109

$

$40,030.75

$40,030.75

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$40,030.75

$40,030.75

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$40,030.75

$40,030.75

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: June 04, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B