Title: Request for approval of change in contract No. 1 with A Morfin Trucking, LLC, for the Yale Stormwater Detention Basin, adding 38 calendar days and resulting in an addition of $258,590 to the contract amount (White Oak Bayou Watershed, Bond ID F-09, Project ID E501-03-00-E001, Job No. 24/0350, Precinct 2, MWBE Contracted Goal: 13.35%).

Primary Department: Flood Control District

Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): E501-03-00-E001

Vendor/Entity Legal Name (if applicable): A Morfin Trucking, LLC

 

MWBE Contracted Goal (if applicable): 13.35%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of change in contract No. 1 with A Morfin Trucking, LLC, for the Yale Stormwater Detention Basin, adding 38 calendar days and resulting in an addition of $258,590 to the contract amount (White Oak Bayou Watershed, Bond ID F-09, Project ID E501-03-00-E001, Job No. 24/0350, Precinct 2, MWBE Contracted Goal: 13.35%).

end

 

Background and Discussion:

The Yale Stormwater Detention Basin is located southeast of the intersection at W. Tidwell Road and Yale Street, in the White Oak Bayou Watershed. This project, along with future improvement projects, will help remove the 500-year area of inundation from an estimated 2,815 structures, 2,520 acres of land and 82.8 miles of roadway. The Yale Stormwater Detention Basin project includes a wet bottom detention basin with an inflow side weir and flap gate outfall pipe, adjacent to E101-00-00 (Little White Oak Bayou).

 

The purpose of this Contract Change is to increase quantities for demolition pay items of remove and

dispose of driveways and sidewalks, asbestos pipe removal, remove and dispose of manholes and

inlets, as well as flowable fill to plug existing channel outfall piping. Due to the significant overgrowth

of vegetation on site the existence of these items was likely not identified in the initial survey. An additional 24 calendar days for the Contractor to clear the concrete for evaluation, field meetings, measurement, demolition, and material haul off.

 

Expected Impact:

This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits. 

 

Alternative Options:

This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/10/2024

352.

Award

 

Location: N/A

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

4.a.2 - Construction Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$258,590

$258,590

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$258,590

$258,590

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$258,590

$258,590

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/22/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Change in Contract and Map