Legislation Details

File #: 26-6292    Version: 1 Name:
Type: Investment Memo Status: Agenda Ready
File created: 9/9/2026 In control: Commissioners Court
On agenda: 9/22/2026 Final action:
Title: Request for approval of a Final Investment Memo for the Plumbing Systems Repair and Replacement projects, for a total authorization of $12,860,000 for FY 2027.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP

Managing Department: County Engineer

Managing Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Plumbing Systems Repair and Replacement

Project ID (if applicable): MF0Z6

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $12,860,000

Total Estimated Project Cost: $34,760,000 (FY 2027-2031)

 

Request Summary:

title

Request for approval of a Final Investment Memo for the Plumbing Systems Repair and Replacement projects, for a total authorization of $12,860,000 for FY 2027.

end

 

 

 

Project Description:

These funds are intended to support new construction in the coming fiscal year and the continuous lifecycle management and resiliency upgrades for county facilities. The projects will identify and address all required upgrades and enhancements of plumbing systems in County Facilities. This includes sewer systems, domestic water supply, fire safety systems, pumps, improving existing equipment with safer, more reliable materials, and installing more efficient fixtures. These projects will ensure the county facilities' plumbing infrastructure is updated, resilient, and functional to ensure support to county residents through the years and upcoming disaster seasons.

Below are the planned allocations; there might be changes in the County’s needs that result in minor operational changes and funding for the projects throughout the Fiscal Year. The County Engineer is authorized to adjust scope and projects at their discretion within the program. Any additional financial authorizations would go through Commissioners Court approval.

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

Annex 65 - Criminal Justice Center - Plumbing and Fixtures Replacements and Upgrades (Phase 1)

            $3,150K

FY 2028

Annex 2 - Plumbing and Fixtures Replacements and Upgrades (Phase 1)

$2,700K

FY2028

Parker Williams Branch Library - Plumbing and Fixtures Replacements and Upgrades

$304K

FY2027

Annex 21 - Wilson Building - Fixtures and Plumbing Infrastructure Replacement and Upgrades (Phase 1)

$156K

FY2028

Annex 84 - Shelia Jackson Lee Admin Building - Fire Water Pump Replacements

$490K

FY2027

Annex 48 - Sylvester Turner Admin Building -Plumbing, Tanks and Related Replacements and Upgrades

$2,641K

FY2028

Annex 44 - Anderson Clayton Building - Plumbing Replacement and Upgrades

$2,250K

FY2028

FY 2027 Authorization

$11,691K

 

Contingency

$1,169K

 

FY 2027 Total Authorization

$12,860K

 

 

Justification & Alternatives:

This program seeks to construct critical plumbing repairs and improvements throughout county facilities that will significantly address the health and safety of building tenants, energy efficiency and resiliency of county facilities.  All projects will upgrade the existing plumbing infrastructure, nearly 30-50 years old, to  significantly more resilient current standards.

Failure to maintain, modernize, and upgrade the County's existing facilities will result in significantly more expensive deferred maintenance, future inflation costs, closure of certain areas, non-code compliance, and, most importantly, risks to life/safety. Plumbing systems are critical and required to support the building infrastructure and to allow occupancy. Domestic supply and wastewater capacity is a building code requirement. Running water and flushing toilets are required to maintain the functionality of a facility; without this critical infrastructure, a facility will be shut down. Savings would be a challenge to calculate because failures are unpredictable. If the facilities are not updated, the severely degraded plumbing will continue to fail affecting the resiliency of facilities and the normal operations or disaster recovery operations.

The Office of the County Engineer (OCE) continues to experience the effects of previous years’ inflation regarding materials and labor for construction projects. The cost of individual materials varied significantly the previous fiscal year due to national and international events; this is expected to continue through the next fiscal year.

Not funding this program would lead to an even greater backlog of deferred maintenance to perform later and, in some cases, could create hazards to life and safety.  Delays in project timeline may increase costs due to increased deterioration of infrastructure, potential bid increases, and an increase in material and labor costs.

 

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.

Justice/Safety Initiative (Goal 1):  Choose an item.

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): T2: Make County buildings more energy efficient.

Housing Initiative (Goal 6): N/A

 

Previous Court Action:

Date

Agenda Item #

Action Taken

8/28/2015

1.o.7

Approved $500K Authorization

9/11/2018

3.f.3

Approved: $500K CP allocation

6/4/2019

CIP

Approved: $2M authorization per Interim CIP

7/9/2019

3.f.5

Approved: $2M CP allocation

12/17/2019

4.i.11

Approved: $1M CP allocation

1/7/2020

II.1.d

Approved: $2M authorization per FY20 CIP

7/14/2020

4.h.6

Approved: $1M CP allocation

3/9/2021

88

Approved: Harris County - Proposed Capital Improvements Program; Facility and Maintenance Projects: Plumbing Systems Repair and Replacement Countywide, pages 281 and 291 ($2,428,570 authorization for FY21-22)

8/24/2021

94

Approved: $1,928,570 incremental authorization reduction; $2,245,000 CP reduction

3/8/2022

113

Approved: Request for approval of a Final Investment Memo for the Plumbing Systems Repair and Replacement Countywide project for an additional $912,000 for a SFY 22 authorization of $1,415,000 for Facilities and Property Maintenance and request for approval of commercial paper funding for Engineering for the project in the additional amount of $495,000 for a total of $2,750,000. (p.13)

10/18/2022

127

Approved: Request for approval of a Final Investment Memo for the Plumbing Systems Repair and Replacement Countywide project for an additional $1,646,000 fora FY 2023 authorization of $2,662,000. 22-6664

8/29/2023

23-4874

Approved: Request for approval of a Final Investment Memo for the Plumbing Systems Repair and Replacement Countywide project for an additional $516,000 for a total FY24 authorization of $2,683,000.

1/23/2025

25-0508

Approved: Request for a Final Investment Memo for the Plumbing Systems Repair and Replacement project (continuous) for an additional incremental authorization of $13,895,000 for a total FY2025 authorization of $15,295,000

3/27/2025

25-1533

Request for approval of commercial paper funding for the Plumbing Repair and Replacement project in the additional amount of $1,990,000 for a total CP funding of $6,390,000.

 

Address: Multiple

Precinct(s): Countywide

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 9/22/2026

Anticipated Implementation Date (if different from Court date): 10/1/2026

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, First Assistant County Attorney-Legal Operations, 8/15/2024

Department Approval by:

Ross Hosket, P.E., CFM, ENV-SP, Director - Building Operations Services

Samuel Peña, Chief Operating Officer

Andreas Peeples, CPC, CCM - Director | Facilities and Construction - Vertical Design and Construction

Erwin Burden, P.E., CFM | Chief of Engineering and Architectural Services, Office of County Engineer

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 9/11/2026

________________________________________

Commercial Paper Request (For OMB use only):

Receiving Department: N/A

Project PeopleSoft ID: N/A

CP Series Description: N/A

OMB Financial Management Contact: N/A