Legislation Details

File #: 25-3497    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 5/28/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval of an award on the basis of low bid to Serco Construction Group, LTD. in the amount of $4,087,575 for erosion and slope failure repairs on Berry Bayou for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (250101), MWBE Contracted Goal: 16.03%.

Primary Department: Purchasing

Primary Department Head/Elected Official: Paige McInnis

 

Secondary Department: Flood Control District

Secondary Department Head/Elected Official: Tina Petersen

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 250101

Vendor/Entity Legal Name (if applicable): Serco Construction Group, LTD.

 

MWBE Contracted Goal (if applicable): 16.03%

MWBE Current Participation (if applicable):

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

 

Request Summary (Agenda Caption):

title

Request for approval of an award on the basis of low bid to Serco Construction Group, LTD. in the amount of $4,087,575 for erosion and slope failure repairs on Berry Bayou for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (250101), MWBE Contracted Goal: 16.03%.

end

 

Background and Discussion:

The scope of this project includes drainage system repairs with major emphasis on earthwork, including but not limited to erosion repair, slope failure repair, removal and disposal of sediment accumulations, granular fill and riprap installation, pipe removal and replacement, outfall structure removal and replacement and related items for the following channels:

•                     C106-00-00-X022 - Whispering Creek Dr. downstream to Forest Oaks Blvd.

•                     C106-00-00-X030 - Ahrens St to Forest Oaks Blvd.

 

Expected Impact:

The objectives of this project include the implementation of proposed construction activity as depicted and specified in the Construction Documents to restore channel functionality by repairing the longitudinal and cross-sectional geometry of the channels.

 

 

 

Alternative Options:

Do not proceed with the project.  The channel conditions will continue to deteriorate causing impacts downstream and to adjacent property.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

5/8/2025

417

Transmittal by Purchasing of a project scheduled for advertising

 

Location: N/A

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Construction Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Tax Revenue - FCD

$

$4,087,575.27

$4,087,575.27

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$4,087,575.27

$4,087,575.27

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$4,087,575.27

$4,087,575.27

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/12/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: John Smaistrla, Project Manager, HCFCD; Maria Heinzmann, Senior Buyer, Harris County Purchasing

 