Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 24103MF36Z01
Vendor/Entity Legal Name (if applicable): Harris County Municipal Utility District No.504
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Harris County Municipal Utility District No. 504 in connection with road construction along Madera Run Parkway from East of Radura Road to West of Hickory Arroyo Drive, UPIN 24103MF36Z01, Precinct 3.
end
Background and Discussion:
This roadway expansion will include construction of approximately 2,150 linear feet of the remaining two lanes of full concrete boulevard section going westbound on Madera Run Parkway from East of Radura Road to West of Hickory Arroyo Drive. Precinct 3 commits to funding 50 % of the total construction cost for the roadway construction. Harris County Municipal Utility District No. 504 commits to contribute 50 % of the total construction cost, and will initiate the design, survey, and permitting for the roadway and fully fund the design. Harris County Municipal Utility District No. 504 will also contract, manage, and utilize Harris County Municipal Utility District No. 504 contractors to construct the project.
Expected Impact:
Safe environment for the public.
Alternative Options:
N/A
Alignment with Goal(s):
x Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
x Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
|
|
|
Location:
Address (if applicable): Madera Run Parkway from East of Radura Road to West of Hickory Arroyo Drive, Houston TX 77346.
Precinct(s): Precinct 3
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
FY 24 |
FY 25 |
Next 3 FYs |
|
Incremental Expenditures (do NOT write values in thousands or millions) |
|
Labor Expenditures |
$ |
$ |
$ |
|
Non-Labor Expenditures |
$750,000.00 |
$ |
$ |
|
Total Incremental Expenditures |
$750,000.00 |
$ |
$ |
|
Funding Sources (do NOT write values in thousands or millions) |
|
Existing Budget |
|
Bonds 2022 Road Bond |
$750,000.00 |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Total Current Budget |
$750,000.00 |
$ |
$ |
|
Additional Budget Requested |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Total Additional Budget Requested |
$ |
$ |
$ |
|
Total Funding Sources |
$750,000.00 |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
|
Additional Positions Requested |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
Anticipated Court Date: January 30, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Bashar Ahmed, Deputy Chief of Staff, HCED.
Attachments (if applicable): Interlocal Agreement