Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Arch-Con Corporation, in connection with 3131 Gulf Freeway (The Hay Center), Houston TX 77003 - New Construction - 2020, Job No. 22/0335, UPIN 21035MF1PA01, Precinct 1.
Attachments: 1. 25-2748-(Substantial Completion)-21035MF1PA01-Arch-Con Corporation-Hay Center-P1

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: Housing and Community Development

Secondary Department Head/Elected Official: Thao Costis, Executive Director Housing and Community Development

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

 

Project ID (if applicable): 21035MF1PA01

Vendor/Entity Legal Name (if applicable): Arch-Con Corporation

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Rate is not 0% and is listed above.

 

Request Summary (Agenda Caption):

title

Transmittal by the Office of the County Engineer of a substantial completion certificate with Arch-Con Corporation, in connection with 3131 Gulf Freeway (The Hay Center), Houston TX 77003 - New Construction - 2020, Job No. 22/0335, UPIN 21035MF1PA01, Precinct 1.

end

 

Background and Discussion:

The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets and Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.

 

Expected Impact:

This action establishes the date on which a capital improvement enters service as a Harris County asset.

 

Alternative Options:

N/A

 

County Strategic Plan Goal:  6. Help residents achieve housing stability.

County Strategic Plan Objective: W: Transition people experiencing homelessness into permanent supportive housing.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): W2: Increase stock of permanent supportive housing.

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/13/2022

22-8009

Awarded Arch-Con Corporation contract Job No, 22/0335 for construction of the Hay Center Campus at 3131 Gulf Freeway, Houston TX 77003

 

Location:

Address (if applicable): 3131 Gulf Freeway, Houston Texas 77003

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/8/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Bullock, Project Manager, Facilities Design & Construction, Office of the County Engineer; Dr. Ronald Lerner, DBA, MScE, LSSBB, IAEng - Director, Facilities Design & Construction, Office of the County Engineer

 

Attachments (if applicable): Certificate of Substantial Completion.