Legislation Details

File #: 26-5272    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 7/24/2026 In control: Commissioners Court
On agenda: 8/6/2026 Final action: 8/6/2026
Title: Request for approval of a Change Investment Memo for the New Katy Service Center project with updated project scope and no additional incremental authorization.

Primary Department: Commissioner, Precinct 4

Primary Department Head/Elected Official: Lesley Briones, Commissioner

Managing Department: Commissioner, Precinct 4

Managing Department Head/Elected Official: Lesley Briones, Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Change Investment Memo

 

Project Name: New Katy Service Center

Project ID (if applicable): MF38E

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: N/A

Total Estimated Project Cost: $750,000.00

 

Request Summary:

title

Request for approval of a Change Investment Memo for the New Katy Service Center project with updated project scope and no additional incremental authorization.

end

 

Project Description:

Precinct 4 has received authorization in FY24 to use commercial paper for a total of $750,000.00 for facility improvements as per OMB’s non-voted commercial paper policy. The authorized budget for the project did not include construction, only design, and needs to be reallocated as per the first table below.

 

 

 

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Approved Authorization

Re-Allocate Authorized Amount to:

Katy Service Center - Design

$413,661.00

Katy Service Center - Construction

$336,339.00

Total

$750,000.00

 

Justification & Alternatives:

The adjustment in existing allocations is necessary to complete the listed project and provide needed services

to serve the community. Since the previous facility was destroyed by fire, the team has been operating out of a temporary building structure that limits efficiency and functionality. The new center will offer a modern workspace, updated technology, and a dedicated electrical room capable of meeting the demands of the entire camp. This facility is critical to supporting the Road and Bridge team in maintaining infrastructure and providing rapid emergency response throughout Precinct 4.

This project supports the following Priority Outcomes and/or Goal Areas:

•                     Justice and Safety: Provides a base of operations for Precinct 5 Constables, enabling timely and effective community engagement.

•                     Governance and Customer Service: Facility improvements will enhance services to the community by providing the Road and Bridge team with the resources needed to ensure dependable infrastructure maintenance and efficient and effective disaster response.

Stakeholder Engagement: Precinct 4 will engage the following stakeholders:

•                     Precinct 4 Road and Bridge Division: To ensure the facility meets operational needs.

•                     Precinct 5 Constable’s Office: To support their workspace and logistical requirements.

Addressing these needs now will ensure the new facility remains safe, functional and beneficial to the entire community for years to come.

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  H4: Consistently embed sustainability considerations in the project planning and design process.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): R3: Strengthen the County’s emergency response function.

Housing Initiative (Goal 6): N/A

 

Previous Court Action:

Date

Agenda Item #

Action Taken

6/12/2025

294

Approval of the Preliminary Investment Memo for the Katy Service Center project for an amount of $750,000.00

                     

Address: 16355 Clay Rd, Houston, TX 77084

Precinct(s): Precinct 4

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$750,000.00

$750,000.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$750,000.00

$750,000.00

$

Additional Budget Request

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$750,000.00

$750,000.00

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/6/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, First Assistant County Attorney-Legal Operations, 5/29/2026

Department Approval by: Jamaal Smith, Chief of Staff, Commissioner Precinct 4

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 7/28/2026

Commercial Paper Request (For OMB use only):

Receiving Department: N/A

Project PeopleSoft ID: N/A

CP Series Description: N/A

OMB Financial Management contact: N/A