Title: Request for approval to execute an agreement with Accelerate Engineering, LLC in the amount of $390,274.59, for professional engineering services to conduct Corridor Study - All In 4 Inner Northwest - Precinct 4 - 2025, UPIN 25208MF3W401, Precinct 4, MWBE Contracted Goal: 21%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

 

Secondary Department: Commissioner, Precinct 4

Secondary Department Head/Elected Official: Leslie Briones, Commissioner                       

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 25208MF3W401

Vendor/Entity Legal Name (if applicable): Accelerate Engineering, LLC

 

MWBE Contracted Goal (if applicable): 21%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Accelerate Engineering, LLC in the amount of $390,274.59, for professional engineering services to conduct Corridor Study - All In 4 Inner Northwest - Precinct 4 - 2025, UPIN 25208MF3W401, Precinct 4, MWBE Contracted Goal: 21%.

end

 

Background and Discussion:

The Inner Northwest area is located within the Spring Branch boundaries of Precinct 4 along Hempstead Highway. This transportation safety study focuses on high-risk traffic accident intersections within the Inner Northwest identified within the previous plan, All In 4 Inner Northwest Community Plan. The study will develop a professional engineering report with 30% design, along with improvement strategies for 4 intersections, aiming to reduce traffic-related fatalities and improve safety through coordinated planning with the City of Houston and community stakeholders.

 

Expected Impact:

This study will establish existing conditions baseline for the Inner Northwest community, including those who live, work, and visit the area, how people move around, and the conditions that support safe, comfortable transportation in the study area. These will be used to develop an approach and initial set of opportunities to create safe intersections in alignment with the Harris County Vision Zero Action Plan.

 

Alternative Options:

Failure to study the intersections for safety and mobility improvements will result in continued congestion and conflicts between passenger automobiles, heavy truck traffic, and pedestrians. 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any): N/A- Vendor Pool Selection

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable):

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$390,274.59

$390,274.59

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$390,274.59

$390,274.59

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$390,274.59

$390,274.59

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 5/14/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Patrick Mandapaka, PhD, AICP, Senior Director of Planning & Development Services, OCE

 

Attachments (if applicable): Agreement & Exhibits