Title: Request for approval to execute an interlocal agreement with 7901 SPRING, LP in connection with Road Improvements - Spring Stuebner Rd from 250' east of Matted Oak View to Avalon Lake Crest Rd - 2026, UPIN 26103SEBTB01, Precinct 3.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official:

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

 

Project ID (if applicable): 26103SEBTB01

Vendor/Entity Legal Name (if applicable): 7901 SPRING, LP

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable):N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable):N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an interlocal agreement with 7901 SPRING, LP in connection with Road Improvements - Spring Stuebner Rd from 250' east of Matted Oak View to Avalon Lake Crest Rd - 2026, UPIN 26103SEBTB01, Precinct 3.

end

 

Background and Discussion:

 

The terms of the developer’s TIA was to enter into a cost share joint participation agreement with Harris County to expand the Spring Stuebner cross section to three-lanes from 250' east of Matted Oak View to Avalon Lake Crest Rd. Harris County will design, construction and manage the project and the developer will fund 40% of the construction cost.

 

Expected Impact:

 

This action will allow the developer and Harris County to enter into a joint participation agreement to expand Spring Stuebner Road to a three-lane cross section.

 

Alternative Options:

The alternative is to not to enter into this agreement and Spring Stuebner Road’s cross section will shift from three lane to two lane then back to three lane.

 

 

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

 

 

 

 

 

 

 

Location:

Address (if applicable): Hufsmith-Kohrville Rd 3 Precinct(s): Choose an item.

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$540,000.00

$540,000.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$540,000.00

$540,000.00 

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$540,000.00

$540,000.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 10/29/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services,

Office of the County Engineer

 

 

Attachments (if applicable):