Legislation Details

File #: 24-4057    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 6/28/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval to execute an agreement with TEDSI Infrastructure Group, Inc., in the amount of $198,178.75 for survey, design, and construction services of a new traffic signal at the intersection of Stuebner Airline Road at Hufsmith Kuykendahl Road, UPIN 24035MF37Y01, Precinct 3, MWDBE Contracted Goal: 20%.
Sponsors: Mony Hossain
Attachments: 1. 24-4057-Consultant-UPIN 24035MF37Y01- Stuebner Airline at Hufsmith Kuykendahl-TEDSI Infrastructure Group, Inc

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 24035MF37Y01

Vendor/Entity Legal Name (if applicable): TEDSI Infrastructure Group

 

MWDBE Contracted Goal (if applicable): 20%

MWDBE Current Participation (if applicable): 0

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with TEDSI Infrastructure Group, Inc., in the amount of $198,178.75 for survey, design, and construction services of a new traffic signal at the intersection of Stuebner Airline Road at Hufsmith Kuykendahl Road, UPIN 24035MF37Y01, Precinct 3, MWDBE Contracted Goal: 20%.

end

 

Background and Discussion:

Traffic signals are installed to improve the operation of an intersection and better facilitate pedestrian activities. As such, the consultant will be tasked with the signal design of the intersection to improve operations. The consultant will be tasked with evaluating pedestrian accessibility through the provision of crosswalks and associated median nose opening adjustments required to facilitate pedestrian activities.

 

Expected Impact:

Designing and constructing a traffic signal at this intersection will improve operations and better facilitate pedestrian activities.

 

Alternative Options:

This location currently operates as a multi-way stop-controlled intersection. An alternative is to not signalize the intersection, which will not provide operational and pedestrian benefits.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/19/2023

105

Approved

 

Location: Stuebner Airline Road at Hufsmith Kuykendahl Road

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Professional Services (Survey and Design)

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$198,178.75

$198,178.75

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$198,178.75

$198,178.75

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$198,178.75

$198,178.75

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: July 15th, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Patrick Mandapaka, PhD, ACIP, Director of Community Resilience & Transportation Planning

Attachments (if applicable): Agreement