File #: 25-3845    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/11/2025 In control: Commissioners Court
On agenda: 6/26/2025 Final action: 6/26/2025
Title: Request for approval of amendment No. 1 with HTS, Inc. Consultants, in the amount of $160,000, to provide additional materials engineering and testing services in support of the White Oak Bayou Federal Flood Damage Reduction Project Channel Modifications Discrete Segment 106, White Oak Bayou from Cole Creek to Hollister Street on HCFCD Unit E100-00-00 (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E006, Agreement No. 2021-104, Precinct 1, Justification for 0% MWBE Participation Goal: 0% - Specialized, Technical, or Unique in Nature).
Attachments: 1. 062625 AMEND HTS 2021-104 PCTS 1 AND 4 backup.pdf

Primary Department: Flood Control District

Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): E100-00-00-E006

Vendor/Entity Legal Name (if applicable): HTS, Inc. Consultants

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  0% - Specialized, Technical, or Unique in Nature

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): HCFCD, HCTRA, HHS

 

Request Summary (Agenda Caption):

title

Request for approval of amendment No. 1 with HTS, Inc. Consultants, in the amount of $160,000, to provide additional materials engineering and testing services in support of the White Oak Bayou Federal Flood Damage Reduction Project Channel Modifications Discrete Segment 106, White Oak Bayou from Cole Creek to Hollister Street on HCFCD Unit E100-00-00 (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E006, Agreement No. 2021-104, Precinct 1, Justification for 0% MWBE Participation Goal:  0% - Specialized, Technical, or Unique in Nature).

end

 

Background and Discussion:

This amendment will provide additional materials engineering and testing services to support construction materials testing for the White Oak Bayou Federal Flood Damage Reduction Project. This project occurs in the 1st quartile under the 2022 Prioritization Framework approved by Commissioners Court. This amendment is to increase the agreement amount and update the fee schedule for materials engineering and testing professional services to allow the project to continue.

 

Expected Impact:

Materials engineering and testing services under this agreement will provide essential quality control and assurance, ensuring that soils and construction materials meet specified standards and performance criteria, ultimately leading to enhanced structural integrity and longevity while reducing risks and costs associated with earthen and material failures. This quality control and assurance will help ensure that flood risk reduction projects are constructed properly.

 

Alternative Options:

The alternative to approving this item would be to select another firm for this assignment, which would result in a lack of materials testing support for this ongoing project and potential project delays.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/15/2020

2.b.2.

ATN

2/9/2021

72.

AGREEMENT

2/26/2021

85.

ATN CORRECTION

 

Location: White Oak Bayou

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

4.a.2 - Construction Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$160,000

$160,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$160,000

$160,000

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$160,000

$160,000

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/26/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Agreement and Map